SEL Grid Configurator Tutorial: TiDL Configuration and Commissioning

SEL Grid Configurator: Complete Guide to TiDL Configuration, I/O Mapping, Topology Design and Commissioning

Table Of Contents
  1. Introduction
  2. 1. What Is SEL Grid Configurator?
  3. 2. Understanding the TiDL Configuration Architecture
  4. 3. Understanding the Two Main Configuration Tasks
  5. 4. Preparing the Project Before Configuration
  6. 5. Installing and Starting SEL Grid Configurator
  7. 6. Creating a TiDL Engineering Project
  8. 7. Adding SEL-TMU Devices
  9. 8. Configuring Physical Connections
  10. 9. Configuring Port Mapping
  11. 10. Configuring Analog I/O Mapping
  12. 11. Configuring Binary Input Mapping
  13. 12. Configuring Binary Output Mapping
  14. 13. Using Custom Aliases
  15. 14. Understanding Multiple SEL-TMU Connections
  16. 15. Reviewing and Validating the Configuration
  17. 16. Sending and Reading Configurations
  18. 17. TiDL Commissioning
  19. 18. Troubleshooting Common Grid Configurator and TiDL Problems
  20. 19. Practical Example: Complete Feeder Configuration Checklist
  21. 20. Official SEL Training and Documentation
  22. Conclusion
  23. Learn SEL Protection and Digital Substation Engineering with Elec-Engg

Introduction

Modern digital substations are changing the way protection engineers design, configure and commission protection systems. One important development is SEL Time-Domain Link (TiDL), a digital secondary system that replaces many conventional copper connections between primary equipment and protection relays with dedicated fiber-optic communication.

At the centre of SEL TiDL engineering is SEL Grid Configurator, a software application used to configure SEL protection devices and engineer TiDL system topologies.

For engineers working with SEL-TMU merging units and TiDL-enabled protection relays, understanding Grid Configurator is essential. It allows engineers to establish physical communication relationships, map remote analog and binary signals to protection relay quantities, and verify the configured TiDL connections.

This guide explains the engineering workflow, using a practical feeder protection example with an SEL-TMU and a compatible SEL-451 TiDL relay.

The article covers:

  • Introduction to SEL Grid Configurator.
  • Software architecture and project organization.
  • Adding SEL-TMU devices and protection relays.
  • TiDL physical and logical connections.
  • Port mapping.
  • Analog current and voltage mapping.
  • Binary input and output mapping.
  • Custom signal aliases.
  • Configuration validation and commissioning.
  • Communication failure checks.
  • Common configuration mistakes.
  • Practical engineering examples.

1. What Is SEL Grid Configurator?

SEL Grid Configurator is an engineering software application developed by Schweitzer Engineering Laboratories (SEL).

It provides a common environment for configuring and commissioning supported SEL devices.

For TiDL applications, it is particularly important because it allows engineers to configure the relationships between:

  • SEL-TMU merging units.
  • TiDL-enabled SEL protection relays.
  • Fiber-optic communication ports.
  • Analog current measurements.
  • Analog voltage measurements.
  • Binary inputs.
  • Binary outputs.

The software supports custom TiDL topologies and provides a way to map SEL-TMU I/O quantities to the corresponding local I/O quantities of the protection relay.

Main engineering functions

FunctionPurpose
Device configurationCreate and manage supported SEL device projects
TiDL topologyDefine the merging units connected to protection relays
Port mappingAssign physical TMU ports to relay communication ports
I/O mappingAssign remote TMU measurements and signals to relay quantities
Custom aliasesUse meaningful names for remote signals
Configuration validationCheck configured connections and hardware
CommissioningSupport the deployment and verification of TiDL configurations
Relay settingsConfigure supported protection and device settings

The exact features available depend on the installed Grid Configurator release and the selected device.

2. Understanding the TiDL Configuration Architecture

Before opening Grid Configurator, engineers should understand the physical architecture of the system.

Consider a simple feeder protection application:

  • One SEL-TMU installed in the substation yard.
  • One compatible SEL-451 TiDL protection relay installed in the control building.
  • Three-phase CT measurements.
  • Three-phase VT measurements.
  • Circuit-breaker status signals.
  • Disconnector status signals.
  • Trip output.

The architecture is:

             SUBSTATION YARD

        CTs                 VTs
         │                   │
         └─────────┬─────────┘
                   │
             ┌───────────┐
             │ SEL-TMU   │
             │ Merging   │
             │ Unit      │
             └─────┬─────┘
                   │
             Fiber-optic link
                   │
             ┌─────▼─────┐
             │ SEL-451   │
             │ TiDL      │
             │ Protection│
             │ Relay     │
             └─────┬─────┘
                   │
             Protection Logic
                   │
             Trip Command
                   │
             Fiber-optic link
                   │
             ┌─────▼─────┐
             │ SEL-TMU   │
             │ Output    │
             └─────┬─────┘
                   │
             Circuit Breaker

This is a conceptual example. The exact number of connections, available ports and signal assignments must be verified against the selected relay and SEL-TMU hardware.

3. Understanding the Two Main Configuration Tasks

One of the most important concepts in Grid Configurator is the difference between port mapping and I/O mapping.

They are related, but they do not perform the same function.

3.1 Port mapping

Port mapping establishes the physical relationship between the communication port on the protection relay and the corresponding fiber port on the SEL-TMU.

For example:

Protection relay portConnected deviceTMU port
Relay Port 6AFeeder 1 TMUPort 2
Relay Port 6BBus Protection TMUPort 2

The example illustrates the mapping concept, not a universal port assignment.

The physical fiber connection must match the port mapping configured in the software.

3.2 I/O mapping

I/O mapping establishes which signal from the SEL-TMU is assigned to which quantity in the protection relay.

For example:

Relay quantitySEL-TMU signal
Phase A currentTMU current input A
Phase B currentTMU current input B
Phase C currentTMU current input C
Phase A voltageTMU voltage input A
Phase B voltageTMU voltage input B
Phase C voltageTMU voltage input C

Binary signals are mapped in a similar way.

For example, a circuit-breaker closed indication acquired by the SEL-TMU can be assigned to the appropriate relay logic quantity.

Remember: Port mapping establishes where the communication comes from. I/O mapping establishes what information the relay receives through that connection.

4. Preparing the Project Before Configuration

A successful TiDL configuration starts with good engineering documentation.

Before opening Grid Configurator, prepare the following:

4.1 Single-line diagram

The single-line diagram should identify:

  • Circuit breakers.
  • Disconnectors.
  • Earthing switches.
  • CTs.
  • VTs.
  • Busbars.
  • Protection relays.
  • Primary equipment locations.

4.2 AC wiring drawings

Prepare the CT and VT wiring drawings.

Verify:

  • CT ratios.
  • CT polarity.
  • CT secondary grounding.
  • VT ratios.
  • VT secondary connections.
  • Phase identification.
  • Test terminal arrangements.

4.3 DC wiring drawings

Prepare the binary input and output wiring diagrams.

Identify:

  • Breaker 52a and 52b contacts.
  • Disconnector position contacts.
  • Earthing switch contacts.
  • Trip circuit.
  • Close circuit.
  • Lockout relay contacts.
  • Auxiliary alarms.

4.4 Fiber-optic connection schedule

Prepare a dedicated fiber schedule.

TMU nameTMU portRelay nameRelay portFiber reference
FEEDER1_TMUPort 2FEEDER1_RELAYPort 6AFO-101
BUS_TMUPort 2FEEDER1_RELAYPort 6BFO-102

These are illustrative identifiers. Use the actual port designations and device compatibility information for the selected hardware.

4.5 I/O list

Prepare a complete signal list with consistent naming.

For example:

SignalTypeDescription
F1_IAAnalogFeeder phase A current
F1_IBAnalogFeeder phase B current
F1_ICAnalogFeeder phase C current
F1_VAAnalogFeeder phase A voltage
F1_VBAnalogFeeder phase B voltage
F1_VCAnalogFeeder phase C voltage
F1_52ABinary inputBreaker closed indication
F1_52BBinary inputBreaker open indication
F1_TRIPBinary outputBreaker trip command

A well-prepared I/O list makes configuration, testing and troubleshooting significantly easier.

5. Installing and Starting SEL Grid Configurator

The first step is to obtain the appropriate software release from SEL.

Before installation:

  1. Check the supported operating system.
  2. Review the software release notes.
  3. Verify compatibility with the selected relay.
  4. Check whether the required device firmware is supported.
  5. Install the required communication drivers and supporting components, if applicable.
  6. Confirm that the software starts correctly.

SEL provides an official introductory eLearning course for Grid Configurator that covers installation, the user interface, device organization and communication configuration.

The software interface and available options may change between releases. Always use the instruction manual corresponding to the installed version.

6. Creating a TiDL Engineering Project

The next task is to establish the device projects and organize the engineering configuration.

A typical project may include:

  • One or more TiDL-enabled protection relays.
  • One or more SEL-TMU merging units.
  • Device identification.
  • Communication relationships.
  • Port mappings.
  • I/O mappings.
  • Relay settings and associated configuration files.

Use meaningful device names.

For example:

  • FDR1_TMU
  • FDR1_RELAY
  • BUS_TMU
  • TRANSFORMER_TMU
  • TR1_RELAY

Avoid names such as TMU1, TMU2 and Relay1 when the project contains many bays. Clear names reduce mistakes during commissioning and maintenance.

7. Adding SEL-TMU Devices

The SEL-TMU is the remote acquisition device in the TiDL system.

When preparing the project, identify each merging unit according to its physical location and role.

For example:

Device namePhysical locationMain purpose
FDR1_TMUFeeder 1 bayFeeder current and voltage acquisition
BUS_TMUBusbar protection panelBus protection measurements
TR1_TMUTransformer bayTransformer measurement acquisition

The configuration should match the actual hardware installed in the substation.

Pay particular attention to the selected SEL-TMU input arrangement:

  • Eight current inputs.
  • Four current inputs and four voltage inputs.

Do not configure a voltage measurement channel that is not physically available on the selected hardware.

8. Configuring Physical Connections

Physical connections are the actual fiber-optic links installed between the SEL-TMU and the protection relay.

For each link, confirm:

  • Correct fiber cable.
  • Correct fiber type.
  • Correct transceiver.
  • Correct TMU port.
  • Correct relay port.
  • Correct cable identification.
  • Correct termination.

SEL’s official Grid Configurator video series includes a dedicated lesson on the physical connections of a TiDL system.

This stage should be completed and checked against the fiber schedule before finalizing logical mappings.

Important: A configuration file cannot compensate for incorrect physical wiring. If the relay expects data from one port but the fiber is connected to another port, the physical and logical arrangements will not match.

9. Configuring Port Mapping

Port mapping is one of the main parts of TiDL engineering.

The purpose is to tell the protection relay which SEL-TMU and which TMU port are associated with each enabled TiDL relay port.

A typical engineering sequence is:

  1. Open the supported relay device project.
  2. Navigate to the TiDL I/O mapping area available for that device.
  3. Enable the applicable TiDL port configuration, where required.
  4. Select the relay communication port.
  5. Select the corresponding SEL-TMU device.
  6. Select the physical TMU port.
  7. Confirm the mapping.
  8. Repeat for the other connected merging units.
  9. Compare the completed mapping with the fiber connection schedule.

Example

Assume the following physical connections:

RelayRelay portTMUTMU port
SEL-451Port 6AFDR1_TMUPort 2
SEL-451Port 6BBUS_TMUPort 2

The configured port mapping must represent these actual connections.

The software’s interface may use different labels depending on the supported device and release.

Why is port mapping important?

Incorrect port mapping can result in:

  • Communication with the wrong merging unit.
  • Missing measurements.
  • Incorrect signal associations.
  • Unexpected device status.
  • Commissioning delays.

Always compare the configuration against the physical fiber schedule.

10. Configuring Analog I/O Mapping

After establishing the communication relationships, engineers must map the analog measurements.

Consider a feeder protection application with three-phase current and voltage measurements.

The SEL-TMU acquires:

  • Phase A current.
  • Phase B current.
  • Phase C current.
  • Phase A voltage.
  • Phase B voltage.
  • Phase C voltage.

These signals must be assigned to the correct relay measurement quantities.

Example: Current mapping

Relay current quantityTMU current signal
IAWFDR1_TMU current A
IBWFDR1_TMU current B
ICWFDR1_TMU current C

The labels in this table are illustrative. Use the actual relay quantity names displayed for the selected device.

Example: Voltage mapping

Relay voltage quantityTMU voltage signal
VAYFDR1_TMU voltage A
VBYFDR1_TMU voltage B
VCYFDR1_TMU voltage C

The actual quantity names depend on the relay configuration.

Engineering checks

Before accepting the mapping, verify:

  1. Correct CT source.
  2. Correct CT phase.
  3. Correct CT polarity.
  4. Correct VT source.
  5. Correct VT phase.
  6. Correct signal scaling.
  7. Correct relay measurement quantity.
  8. Correct physical wiring.

An incorrect phase assignment can affect directional, distance, differential and other protection functions.

11. Configuring Binary Input Mapping

Binary inputs are used to transfer field status information from the SEL-TMU to the protection relay.

For example, a feeder bay may require:

  • Circuit-breaker closed status.
  • Circuit-breaker open status.
  • Disconnector closed status.
  • Disconnector open status.
  • Earthing switch status.
  • Local/remote selector status.

Example binary input mapping

Relay logic signalSEL-TMU inputDescription
F1_52ATMU input 1Breaker closed
F1_52BTMU input 2Breaker open
F1_DSTMU input 3Disconnector status
F1_ESTMU input 4Earthing switch status
F1_LOCALTMU input 5Local/remote selector

The exact signal assignment must follow the approved DC wiring diagrams and the relay’s supported logic quantities.

Why are binary signals important?

Protection and control systems often use binary signals for:

  • Breaker control.
  • Interlocking.
  • Breaker-failure logic.
  • Protection blocking.
  • Alarm generation.
  • Bay control.
  • Event recording.

A wrong binary mapping can cause serious control or protection problems.

For example, if a breaker closed indication is incorrectly assigned to a breaker open signal, the relay’s control and protection logic may operate incorrectly.

12. Configuring Binary Output Mapping

Binary outputs are used to transfer commands from the protection relay to the SEL-TMU output contacts.

For example, the protection relay may send a trip command that operates an output contact on the merging unit.

A simplified signal chain is:

Protection Element
       │
       ▼
Relay Trip Logic
       │
       ▼
TiDL Communication
       │
       ▼
SEL-TMU Binary Output
       │
       ▼
Breaker Trip Circuit
       │
       ▼
Circuit Breaker

Example output mapping

Relay commandTMU outputApplication
TRIP_1Output 1Breaker trip coil 1
TRIP_2Output 2Breaker trip coil 2
CLOSEOutput 3Breaker close command
ALARMOutput 4Alarm output

This table is an illustrative engineering example, not a universal output assignment.

Important trip circuit considerations

When using a remote output for tripping, engineers must verify:

  • Output contact rating.
  • DC supply voltage.
  • Trip coil current.
  • Required operating time.
  • Trip circuit supervision.
  • Circuit-breaker auxiliary contacts.
  • Communication failure behavior.
  • Redundancy requirements.
  • Protection scheme requirements.

The trip circuit must be tested under an approved commissioning procedure before the system is placed into service.

13. Using Custom Aliases

Custom aliases are a useful feature of TiDL engineering.

Instead of using generic channel names, engineers can assign meaningful names based on the physical location or function of the signal.

For example:

Generic signalCustom alias
Current input 1FDR1_IA
Current input 2FDR1_IB
Current input 3FDR1_IC
Voltage input 1BUS_VA
Binary input 1CB52A_CLOSED
Binary input 2CB52B_OPEN

Custom aliases can improve:

  • Configuration readability.
  • Signal identification.
  • Commissioning efficiency.
  • Troubleshooting.
  • Project documentation.
  • Maintenance.

SEL specifically describes custom naming of SEL-TMU I/O quantities as a way to make mapping more intuitive.

Use a consistent naming convention throughout the project. The names should match the engineering drawings wherever practical.

14. Understanding Multiple SEL-TMU Connections

A TiDL-enabled relay can acquire information from multiple merging units, subject to its supported hardware and configuration.

For example, a transformer protection application may require measurement acquisition from more than one transformer terminal.

The topology could contain:

  • Transformer HV-side TMU.
  • Transformer LV-side TMU.
  • Transformer tertiary-side TMU, where required.
  • Compatible transformer protection relay.

Each merging unit must be associated with the correct communication port and signal assignments.

Example transformer current mapping

Protection relay inputSource
HV phase A currentHV_TMU
HV phase B currentHV_TMU
HV phase C currentHV_TMU
LV phase A currentLV_TMU
LV phase B currentLV_TMU
LV phase C currentLV_TMU

The actual protection scheme may require additional inputs, depending on the transformer configuration and protection functions.

The same principle applies to bus differential protection, where current measurements from multiple bays must be correctly assigned to the bus protection relay.

15. Reviewing and Validating the Configuration

After completing the port and I/O mappings, review the entire configuration.

The validation process should include:

Device review

  • Correct relay model.
  • Correct hardware configuration.
  • Correct SEL-TMU model.
  • Correct device identification.
  • Supported firmware and software versions.

Communication review

  • Correct physical fiber connections.
  • Correct relay port mapping.
  • Correct TMU port mapping.
  • Correct device associations.
  • No unintended duplicate assignments.

Analog review

  • Correct current mapping.
  • Correct voltage mapping.
  • Correct phase assignment.
  • Correct polarity.
  • Correct measurement scaling.

Binary review

  • Correct input assignment.
  • Correct normal state.
  • Correct output assignment.
  • Correct control logic.
  • Correct breaker interface.

Documentation review

  • Approved fiber schedule.
  • Approved AC drawings.
  • Approved DC drawings.
  • Approved I/O list.
  • Approved relay settings.
  • Correct configuration revision.

SEL Grid Configurator provides tools to verify configured connections and hardware. However, software validation does not replace independent engineering checks or physical commissioning tests.

16. Sending and Reading Configurations

When the project configuration is ready, the engineer must follow the supported device connection and deployment procedure.

A controlled workflow should include:

  1. Save the engineering project.
  2. Confirm the selected device and configuration.
  3. Connect to the appropriate device through a supported interface.
  4. Read the existing device configuration when required.
  5. Compare existing and intended configurations.
  6. Confirm the correct project revision.
  7. Send the approved configuration.
  8. Verify the device response and configuration status.
  9. Save the final files and records.

The exact commands and workflow depend on the relay and Grid Configurator version.

Never overwrite an in-service relay configuration without an approved change procedure and a recoverable backup.

17. TiDL Commissioning

Configuration is only one part of commissioning.

A complete commissioning test must verify the physical equipment, communication links, measurements, binary signals, protection logic and output circuits.

17.1 Physical inspection

Check:

  • SEL-TMU installation.
  • Auxiliary power supply.
  • CT wiring.
  • VT wiring.
  • Binary input wiring.
  • Binary output wiring.
  • Fiber-optic connections.
  • SFP transceivers.
  • Device identification.
  • Earthing and panel installation.

17.2 Communication testing

Verify that:

  • The relay identifies the connected SEL-TMU.
  • The configured ports correspond to physical connections.
  • The expected measurements are available.
  • Device diagnostics show acceptable status.
  • Communication alarms are clear.
  • Communication restoration behaves as expected.

17.3 Analog measurement testing

Use a suitable secondary injection test set to apply current and voltage signals.

Check:

  • Phase A current.
  • Phase B current.
  • Phase C current.
  • Phase A voltage.
  • Phase B voltage.
  • Phase C voltage.

Compare the injected values with the measurements displayed by the relay.

Verify phase angles, polarity, magnitude and signal assignment.

17.4 Binary input testing

Operate the appropriate field contacts or use an approved test method.

Verify that each input changes state correctly at the relay.

For example:

  • Breaker open.
  • Breaker closed.
  • Disconnector open.
  • Disconnector closed.
  • Earthing switch open.
  • Earthing switch closed.

17.5 Binary output testing

Test each configured output.

Verify the complete chain from relay logic to the intended output contact.

For trip and close outputs, use an approved test procedure that prevents unintended breaker operation.

17.6 Protection function testing

Finally, test the protection functions using suitable secondary injection methods.

For a feeder relay, this may include:

  • Phase overcurrent.
  • Earth-fault overcurrent.
  • Directional overcurrent.
  • Distance protection, where applicable.
  • Breaker-failure logic.
  • Trip logic.

The test plan must reflect the functions actually enabled in the selected relay.

18. Troubleshooting Common Grid Configurator and TiDL Problems

ProblemPossible causeEngineering action
SEL-TMU not identifiedPhysical fiber connection or port assignment problemVerify physical connections, port mapping and device status
No current measurementsIncorrect current I/O mappingCheck TMU channel assignment and relay quantity mapping
Incorrect phase sequenceIncorrect CT or VT phase assignmentVerify AC wiring and perform injection testing
Wrong binary indicationIncorrect input mapping or field contact wiringCheck DC diagrams, input polarity and signal assignment
Trip output does not operateIncorrect output mapping or logicVerify relay logic, TMU output and trip circuit
Configuration cannot be sentUnsupported device, firmware or connection setupCheck software release, device support and connection method
Wrong TMU assigned to a relay portIncorrect port mappingCompare the configuration with the fiber schedule
Measurements disappear after fiber disconnectionCommunication link failureCheck the fiber, SFP, device diagnostics and failure response
Configuration differs from approved drawingsProject revision or engineering errorReview change records and restore the approved configuration
Unexpected protection operationIncorrect measurement or logic assignmentCheck CT/VT polarity, channel mapping, settings and protection logic

19. Practical Example: Complete Feeder Configuration Checklist

Consider a feeder with one SEL-TMU and one compatible SEL-451 TiDL relay.

The engineer should complete the following activities:

Project preparation

  • Prepare the single-line diagram.
  • Prepare AC wiring drawings.
  • Prepare DC wiring drawings.
  • Prepare the fiber schedule.
  • Prepare the I/O list.
  • Verify device compatibility.

Hardware and connections

  • Install the SEL-TMU.
  • Connect CT circuits.
  • Connect VT circuits, if applicable.
  • Connect binary inputs.
  • Connect binary outputs.
  • Install compatible fiber transceivers.
  • Connect the fiber-optic links.

Grid Configurator

  • Create the engineering project.
  • Add the supported protection relay.
  • Establish the TiDL topology.
  • Configure port mapping.
  • Configure current I/O mapping.
  • Configure voltage I/O mapping.
  • Configure binary input mapping.
  • Configure binary output mapping.
  • Assign meaningful aliases.
  • Review the configuration.

Commissioning

  • Verify communication.
  • Test current measurements.
  • Test voltage measurements.
  • Test binary inputs.
  • Test binary outputs.
  • Test protection functions.
  • Test trip logic.
  • Verify communication failure response.
  • Save final configuration files.

20. Official SEL Training and Documentation

SEL provides official resources that can help engineers learn Grid Configurator and TiDL engineering.

Official TiDL configuration flyer:

https://selinc.com/products/tmu

SEL Grid Configurator video training:

https://video.selinc.com/support/category/videos/grid-configurator

The official TiDL configuration video series includes:

  1. Setting Up a TiDL System – Part 1: Physical Connections.
  2. Setting Up a TiDL System – Part 2: Logical Connections.
  3. Setting Up a TiDL System – Part 3: Commissioning.

SEL Grid Configurator introductory eLearning:

https://selinc.com/selu/courses/esw/125

This complimentary course introduces the software, installation, user interface, device configuration, communication setup and relay settings.


Conclusion

SEL Grid Configurator is an important engineering tool for designing and commissioning TiDL-based digital secondary systems.

The most important tasks are establishing the correct topology, configuring physical port relationships, mapping analog and binary signals, and validating the complete configuration.

For protection engineers, the key is to maintain consistency between the physical substation wiring, the fiber connection schedule, the Grid Configurator project and the relay protection logic.

A successful TiDL installation is not simply a working fiber connection. It is a fully tested protection and control system in which every measurement, status signal and control command is correctly assigned and verified.

Learn SEL Protection and Digital Substation Engineering with Elec-Engg

Elec-Engg provides practical training in power system protection, SEL relays, substation automation, IEC 61850 and digital substation engineering.

Training subjects include:

  • SEL protection relay configuration and applications.
  • SEL Grid Configurator.
  • SEL TiDL and SEL-TMU merging units.
  • IEC 61850 MMS, GOOSE and Sampled Values.
  • Protection relay testing and commissioning.
  • Practical engineering using OMICRON CMC and relay configuration software.

Online training can be arranged based on the required subject and participants’ experience.

Visit https://elec-engg.com/ or contact us for information about customized technical training.


Leave a Comment

Your email address will not be published. Required fields are marked *

Scroll to Top