MMS, GOOSE, SCL Configuration, Testing and Troubleshooting
1. Introduction
IEC 61850 is an international communication standard designed for protection, control, monitoring and automation systems in electrical substations.
Modern protection relays are no longer isolated devices that only measure electrical quantities and operate circuit breakers. They are intelligent electronic devices (IEDs) capable of exchanging information with other protection relays, bay controllers, station controllers, SCADA systems and engineering workstations.
GE Multilin protection relays support various IEC 61850 communication capabilities, depending on the relay family, hardware configuration and firmware version.
Through IEC 61850, engineers can implement:
- Protection signal exchange between IEDs.
- High-speed interlocking using GOOSE.
- Circuit breaker and disconnector status monitoring.
- Measurement transmission to SCADA.
- Remote control and supervision.
- Disturbance and event reporting.
- Substation automation and distributed control.
- Communication between protection and control systems.
Understanding IEC 61850 is therefore essential for engineers working with modern GE Multilin protection systems.
2. Understanding the IEC 61850 Architecture
IEC 61850 defines a standardized information model and communication services for substation automation.
A typical IEC 61850-based substation consists of three functional levels.
2.1 Process Level
The process level interfaces directly with primary electrical equipment.
Typical equipment includes:
- Current transformers (CTs).
- Voltage transformers (VTs).
- Circuit breakers.
- Disconnectors.
- Earthing switches.
- Merging units.
- Process interface devices.
Signals such as breaker position, current, voltage and trip commands can be exchanged between process-level equipment and bay-level IEDs.
2.2 Bay Level
The bay level contains protection and control IEDs.
Examples include:
- GE Multilin protection relays.
- Transformer protection relays.
- Feeder protection relays.
- Generator protection relays.
- Bay control units.
- Metering IEDs.
These devices perform protection, control, measurement and communication functions.
2.3 Station Level
The station level provides centralized supervision and control.
Typical equipment includes:
- SCADA servers.
- HMI workstations.
- Station controllers.
- Engineering workstations.
- Gateway devices.
- Network switches.
3. IEC 61850 Data Model
One of the most important concepts in IEC 61850 is its standardized data model.
Instead of identifying signals only by physical terminals or manufacturer-specific registers, IEC 61850 organizes information using logical devices, logical nodes, data objects and data attributes.
The hierarchy is:
- Physical IED.
- Logical Device (LD).
- Logical Node (LN).
- Data Object (DO).
- Data Attribute (DA).
For example, a circuit breaker can be represented using the logical node XCBR.
| Element | Example |
|---|---|
| IED | GE protection relay |
| Logical Device | PROT |
| Logical Node | XCBR1 |
| Data Object | Pos |
| Data Attribute | stVal |
A typical IEC 61850 reference could look like:
IED1PROT/XCBR1.Pos.stVal
This reference represents the circuit breaker position status.
Other important logical nodes include:
| Logical Node | Function |
|---|---|
| PTOC | Time overcurrent protection |
| PIOC | Instantaneous overcurrent protection |
| PDIF | Differential protection |
| PDIS | Distance protection |
| PTRC | Protection trip conditioning |
| XCBR | Circuit breaker |
| XSWI | Switch or disconnector |
| MMXU | Measurement |
| MMTR | Metering |
| CSWI | Switch control |
| GGIO | Generic process I/O |
| LPHD | Physical device information |
| LLN0 | Logical device common functions |
The actual logical nodes available depend on the relay model and implemented IEC 61850 edition.
4. IEC 61850 Communication Services
Three important communication mechanisms are commonly encountered in IEC 61850 substations.
4.1 MMS – Manufacturing Message Specification
MMS is used for client-server communication.
Typical applications include:
- Reading measurements.
- Reading relay status.
- Retrieving protection information.
- Monitoring alarms.
- Operating circuit breakers.
- Receiving reports and events.
MMS generally operates over TCP/IP using Ethernet networks.
For example, a SCADA system can communicate with a GE Multilin relay to retrieve:
- Phase currents.
- Phase voltages.
- Frequency.
- Active and reactive power.
- Breaker status.
- Protection pickup status.
- Protection trip status.
4.2 GOOSE – Generic Object Oriented Substation Event
GOOSE is designed for fast communication between IEDs.
It is particularly useful for:
- Interlocking.
- Breaker failure initiation.
- Busbar protection.
- Direct transfer trip.
- Protection blocking.
- Fast trip signal exchange.
Unlike conventional MMS client-server communication, GOOSE uses publisher-subscriber communication.
For example:
A transformer protection relay detects an internal transformer fault and publishes a GOOSE trip signal.
Other IEDs subscribe to this message and perform the required actions.
4.3 Sampled Values (SV)
Sampled Values communication is used to transmit digitized current and voltage measurements over Ethernet.
Typical applications include:
- Digital substations.
- Merging units.
- Process bus architectures.
- Protection and metering applications.
SV implementation must be verified against the specific GE Multilin relay model. It should not be assumed that every relay supporting IEC 61850 also supports Sampled Values.
5. GOOSE Engineering and Configuration
GOOSE engineering is one of the most important practical aspects of IEC 61850 commissioning.
Consider the following example.
Application: Transformer Differential Protection and Circuit Breaker Tripping
A transformer differential relay detects an internal fault.
The relay publishes a GOOSE message containing the trip information.
The receiving feeder or circuit breaker IED subscribes to this message and processes the trip command.
The engineering process generally includes:
- Identify the transmitting IED.
- Identify the receiving IED.
- Define the required logical node signals.
- Configure the GOOSE dataset.
- Configure the GOOSE control block.
- Assign multicast communication parameters.
- Configure the receiving subscription.
- Verify signal mapping.
- Download the configuration.
- Perform end-to-end functional testing.
Important GOOSE parameters include:
| Parameter | Description |
|---|---|
| GoCB | GOOSE Control Block |
| DataSet | Collection of transmitted signals |
| GoID | GOOSE message identifier |
| APPID | Application identifier |
| MAC Address | Multicast destination address |
| VLAN ID | Virtual LAN identification |
| VLAN Priority | Ethernet traffic priority |
| MinTime | Minimum retransmission interval |
| MaxTime | Maximum retransmission interval |
| ConfRev | Configuration revision |
Important engineering consideration: GOOSE communication must be tested under normal conditions, during signal transitions, and following communication interruptions.
6. SCL Files and IEC 61850 Engineering
Substation Configuration Language (SCL) is used to describe IEC 61850 system configurations.
SCL files are based on XML.
Important file types include:
| File | Purpose |
|---|---|
| ICD | IED Capability Description |
| IID | Instantiated IED Description |
| CID | Configured IED Description |
| SCD | Substation Configuration Description |
| SSD | System Specification Description |
6.1 ICD File
An ICD file describes the IEC 61850 capabilities of an IED.
It typically contains information about:
- Logical devices.
- Logical nodes.
- Data objects.
- Data attributes.
- Communication capabilities.
- Supported services.
6.2 CID File
A CID file contains the configuration intended for a particular IED.
It is generally used when transferring an engineered configuration to the device.
6.3 SCD File
An SCD file represents the overall substation configuration.
It can include:
- Substation topology.
- IED descriptions.
- Communication networks.
- GOOSE configurations.
- Report configurations.
- Data mappings.
7. Engineering GE Multilin Relays for IEC 61850
The exact engineering procedure depends on the GE Multilin relay family and the supported configuration software.
Relevant relay families include:
- GE Multilin UR Series.
- GE Multilin 8 Series.
- GE Multilin 3 Series.
- GE Multilin 850.
- GE Multilin 869.
- GE Multilin 845.
Not every model or firmware version supports the same IEC 61850 functions.
Before starting an engineering project, verify:
- IEC 61850 support in the exact relay model.
- Communication hardware availability.
- Firmware compatibility.
- Supported IEC 61850 edition.
- Available logical nodes.
- Supported MMS and GOOSE services.
- Required configuration software.
8. Testing and Commissioning
IEC 61850 testing should not be limited to checking whether an Ethernet connection is established.
A successful ping does not prove that GOOSE or MMS communication is functioning correctly.
A proper commissioning procedure should include the following tests.
| Test | Purpose |
|---|---|
| Ethernet connectivity | Verify physical and IP connectivity |
| MMS connection | Verify client-server communication |
| Data reading | Confirm measurements and status |
| Report testing | Verify event reporting |
| GOOSE publishing | Verify transmitted messages |
| GOOSE subscription | Verify received messages |
| Signal mapping | Confirm correct signal assignment |
| Trip testing | Verify actual protection operation |
| Communication failure | Verify failure response |
| Time synchronization | Verify correct event timestamps |
8.1 Practical GOOSE Test Example
Assume the following arrangement:
- IED-1: Transformer protection relay.
- IED-2: Feeder protection relay.
- IED-3: Circuit breaker control IED.
The objective is to transmit a transformer trip command to the relevant circuit breaker control IED.
Testing procedure:
- Confirm that all IEDs are communicating.
- Verify the GOOSE publisher configuration.
- Verify the receiver subscription.
- Inject or simulate the required protection condition.
- Confirm that the transmitting IED changes its GOOSE data.
- Monitor the receiving IED.
- Verify that the mapped trip signal operates.
- Confirm the circuit breaker trip output.
- Record the event timestamps.
- Repeat the test after restoring the normal condition.
For critical protection functions, the test should also verify the complete signal path, including the receiving logic, output contact, trip circuit and circuit breaker operation where appropriate.
9. Common IEC 61850 Problems and Troubleshooting
Communication problems can occur even when all IEDs appear to be connected to the network.
| Problem | Possible Cause | Recommended Check |
|---|---|---|
| MMS connection failure | IP or port configuration | Check network settings and client connection |
| GOOSE not received | Incorrect subscription | Check dataset and control block |
| GOOSE quality invalid | Quality attribute or data issue | Inspect received data quality |
| Wrong signal operation | Incorrect mapping | Verify logical node references |
| GOOSE timeout | Network interruption | Check retransmission and supervision |
| Incorrect timestamps | Time synchronization issue | Check SNTP or PTP configuration |
| Configuration mismatch | Different configuration revisions | Compare ConfRev values |
| Intermittent communication | Network congestion or switching issue | Inspect Ethernet network |
| No communication after download | Incorrect CID or device configuration | Verify configuration compatibility |
Useful troubleshooting tools include:
- Wireshark.
- OMICRON IEDScout.
- Ethernet network diagnostic tools.
- Relay event records.
- Relay communication diagnostics.
- Network switch monitoring.
10. Cybersecurity Considerations
IEC 61850 communication introduces important cybersecurity requirements.
Protection and control engineers should consider:
- Network segmentation.
- VLAN configuration.
- Access control.
- Secure engineering access.
- Firmware management.
- Network monitoring.
- Configuration backup.
- Physical security of communication ports.
- IEC 62351 security requirements where supported.
IEC 61850 communication should be designed as part of the overall substation cybersecurity architecture, not treated as an isolated networking task.
11. Practical Engineering Recommendations
Based on practical substation automation and protection engineering requirements, the following recommendations are important:
- Always verify the IEC 61850 capabilities of the exact relay model.
- Keep backup copies of ICD, CID and SCD files.
- Maintain consistent naming conventions for IEDs and signals.
- Document all GOOSE publishers and subscribers.
- Avoid unnecessary GOOSE signals and datasets.
- Verify VLAN and multicast configurations.
- Test communication failure scenarios.
- Check configuration revision consistency.
- Perform end-to-end testing before energization.
- Keep the final approved configuration and commissioning records.
12. Conclusion
IEC 61850 has become a fundamental technology in modern substation automation.
For GE Multilin protection systems, understanding MMS, GOOSE, logical nodes, datasets, control blocks and SCL engineering is essential for successful protection integration and commissioning.
Protection engineers must understand not only how to configure communication parameters but also how to verify that the exchanged information produces the correct protection and control actions.
A reliable IEC 61850 system requires proper engineering, configuration management, network design, testing and documentation.