NARI Relay Settings, Testing & Commissioning

NARI Relay Settings, Testing & Commissioning: Complete Engineering Guide to Protection Settings, Secondary Injection, Binary I/O, CT/VT Verification, GOOSE Testing, End-to-End Testing and Fault Analysis

Table Of Contents
  1. 1. Understanding NARI Relay Setting Files
  2. 2. Protection Setting Calculation and Verification
  3. 3. Setting Group Management
  4. 4. Binary Input and Output Testing
  5. 5. CT and VT Circuit Verification
  6. 6. Secondary Injection Testing
  7. 7. Protection Function Testing
  8. 8. Trip Circuit Verification
  9. 9. GOOSE Testing
  10. 10. End-to-End Protection Testing
  11. 11. Fault Record Analysis
  12. 12. Commissioning Checklist and Test Reports
  13. NARI relay testing and commissioning checklist
  14. 13. Best Practices for NARI Relay Testing and Commissioning
  15. 14. Applicable IEC Standards and Technical References
  16. 15. NARI Protection Relay Testing and Commissioning Training by Elec-Engg
  17. 16. Conclusion

NARI Relay Settings, Testing & Commissioning is an essential part of the engineering lifecycle of modern electrical protection systems. Correct relay settings, accurate instrument transformer connections, reliable binary input and output circuits, properly configured communication signals and systematic commissioning tests are necessary to ensure that protection systems operate correctly during normal operating conditions and electrical faults.

NARI provides protection and control equipment for applications including transmission lines, distribution feeders, power transformers, generators, busbars and other electrical installations. Its PCS protection and control product families include different relay models designed for specific protection applications.

However, protection functions, setting parameters, setting-file formats, engineering software, test interfaces and communication capabilities vary between NARI models and firmware versions. Engineers must therefore use the applicable product manuals and approved project documentation rather than assume that all PCS relays have identical settings or testing procedures.

This comprehensive article explains the practical engineering workflow for NARI protection relay settings, testing and commissioning. It covers setting calculations, setting-file management, protection coordination, CT and VT circuit verification, secondary injection, binary I/O testing, trip circuit verification, GOOSE testing, end-to-end protection testing, fault record analysis and final commissioning documentation.

1. Understanding NARI Relay Setting Files

1.1 Introduction to Protection Relay Settings

Protection relay settings define how a relay detects abnormal electrical conditions and initiates the appropriate protection response.

A protection relay continuously monitors electrical quantities such as:

  • Phase currents.
  • Residual and earth fault currents.
  • Phase voltages.
  • Frequency.
  • Active and reactive power.
  • Impedance.
  • Differential current.
  • Negative-sequence quantities.

When the measured quantities satisfy the configured protection operating criteria, the relay initiates an alarm, trip command, blocking signal or another configured action.

The settings determine the operating characteristics of each protection function.

For example, an overcurrent protection function may include:

  • Pickup current.
  • Time delay.
  • Operating curve.
  • High-set current.
  • High-set time delay.
  • Directional supervision.
  • Blocking conditions.
  • Reset characteristics.

1.2 NARI Protection Relay Setting Structure

Depending on the product, a NARI relay configuration may include several categories of parameters.

Setting categoryTypical parameters
System configurationRated frequency, CT and VT ratios
Protection settingsPickup values and time delays
Protection characteristicsCurves, slopes and operating zones
Logic settingsBlocking, permissive and trip logic
Binary inputsSignal assignments and polarity
Binary outputsTrip, alarm and indication mapping
CommunicationIP addresses and communication services
IEC 61850Datasets, GOOSE and reporting
ControlBreaker and switchgear control
RecordingEvent and disturbance recording

Not every parameter category is available in every NARI relay.

1.3 Understanding Setting Files

A setting file contains the configuration information used by a protection relay or its engineering software.

Depending on the model and engineering platform, settings may be stored in manufacturer-specific project files, device configuration files, exported reports or other supported formats.

A typical engineering project should maintain:

  1. Original relay configuration.
  2. Approved protection setting calculations.
  3. Final setting file.
  4. Relay configuration backup.
  5. Binary input/output mapping.
  6. Communication configuration.
  7. IEC 61850 configuration, where applicable.
  8. Commissioning test results.

1.4 Setting File Management

A recommended file management structure is:

Substation_Project
 |
 +-- 01_Design
 |    |
 |    +-- Single_Line_Diagram
 |    +-- Protection_Philosophy
 |
 +-- 02_Settings
 |    |
 |    +-- Calculation_Report
 |    +-- Approved_Settings
 |    +-- Relay_Setting_Files
 |
 +-- 03_Configuration
 |    |
 |    +-- Binary_IO
 |    +-- Communication
 |    +-- IEC61850
 |
 +-- 04_Testing
 |    |
 |    +-- Secondary_Injection
 |    +-- Protection_Functions
 |    +-- GOOSE
 |
 +-- 05_Commissioning
      |
      +-- Test_Reports
      +-- As_Built_Configuration
      +-- Final_Backups

1.5 Before Modifying a Relay Setting File

Before making any changes:

  • Identify the exact NARI relay model.
  • Verify the firmware version.
  • Obtain the correct engineering software.
  • Back up the existing configuration.
  • Obtain the approved setting calculation.
  • Confirm CT and VT ratios.
  • Confirm system frequency.
  • Check the relay’s current configuration.
  • Record the existing setting group.
  • Obtain the necessary authorization.

Never modify an in-service relay configuration without an approved engineering and operational procedure.

1.6 Setting File Comparison

Comparing the existing and revised settings is an important quality-control activity.

For example:

ParameterExistingRevised
Phase OC pickup1.20 A1.50 A
Earth fault pickup0.20 A0.25 A
Time multiplier0.100.15
High-set pickup8.0 A10.0 A

These are illustrative values only.

The engineer should identify:

  • Changed parameters.
  • Unchanged parameters.
  • New protection functions.
  • Disabled functions.
  • Changed logic.
  • Changed CT/VT ratios.
  • Changed communication parameters.

Every modification should be checked against the approved calculation and setting document.

2. Protection Setting Calculation and Verification

2.1 Introduction

Protection setting calculation is the process of determining suitable operating parameters for protection functions.

The objective is to ensure that the protection system:

  • Detects faults reliably.
  • Operates within the required time.
  • Remains stable during normal operating conditions.
  • Coordinates with upstream and downstream protection.
  • Avoids unnecessary tripping.
  • Provides adequate backup protection.

The settings must be based on the electrical network design, equipment ratings, fault studies and protection philosophy.

2.2 Required Engineering Information

Before calculating settings, collect:

  • Single-line diagram.
  • Transformer ratings.
  • Generator ratings, where applicable.
  • Cable and overhead line data.
  • CT ratios and classes.
  • VT ratios.
  • Minimum and maximum fault currents.
  • Maximum load current.
  • System grounding arrangement.
  • Neutral earthing impedance.
  • Circuit breaker operating times.
  • Upstream and downstream protection settings.
  • Network operating configurations.

2.3 Overcurrent Protection (ANSI 50/51)

Overcurrent protection is commonly used for feeder, transformer and backup protection.

The main settings include:

  • Pickup current.
  • Operating time.
  • Time-current characteristic.
  • Time multiplier setting.
  • High-set instantaneous pickup.
  • Directional supervision, where required.

For a secondary-current-based relay, the conversion from primary to secondary current is:

\[ I_s=\frac{I_p}{CTR} \]

Where:

  • \(I_s\) = Secondary current.
  • \(I_p\) = Primary current.
  • \(CTR\) = CT ratio.

Example

Consider a feeder with:

  • CT ratio: 600/1 A.
  • Required primary pickup: 480 A.

The secondary pickup is:

\[ I_s=\frac{480}{600}=0.8A \]

Therefore, the relay pickup setting is 0.8 A, assuming the relay setting is expressed in secondary amperes and the CT ratio is correctly configured.

2.4 Inverse-Time Overcurrent Protection

IEC inverse-time protection curves are commonly used for coordination.

A general IEC inverse-time equation is:

\[ t=TMS\times\frac{k}{(I/I_s)^\alpha-1} \]

Where:

  • \(t\) = Operating time.
  • \(TMS\) = Time multiplier setting.
  • \(I\) = Measured current.
  • \(I_s\) = Pickup current.
  • \(k\) and \(\alpha\) = Curve constants.

Typical IEC curve characteristics include:

Curve\(k\)\(\alpha\)
Standard inverse0.140.02
Very inverse13.51
Extremely inverse802

The exact curve implementation and equation must be checked against the relay manual and selected standard.

2.5 Earth Fault Protection (ANSI 50N/51N)

Earth fault protection detects current flowing through the neutral or residual current path.

The setting calculation depends on:

  • System grounding.
  • CT arrangement.
  • Minimum earth fault current.
  • Maximum residual current under normal conditions.
  • Protection sensitivity.
  • Coordination requirements.

For a three-phase residual connection:

\[ 3I_0=I_A+I_B+I_C \]

The relay may obtain the residual current from three phase CTs or a dedicated neutral CT, depending on the application.

2.6 Differential Protection (ANSI 87)

Differential protection compares currents entering and leaving a protected zone.

The operating principle is based on the difference between the compensated currents.

A simplified differential current expression is:

\[ I_{diff}=|I_1-I_2| \]

Practical differential protection uses restraint or bias characteristics to maintain stability during external faults and CT saturation.

Important settings include:

  • Minimum differential pickup.
  • Bias slope.
  • High-set differential pickup.
  • CT ratio compensation.
  • Vector group compensation.
  • Zero-sequence compensation.
  • Inrush restraint or blocking.
  • Overexcitation restraint, where applicable.

For NARI transformer and line differential relays, the exact compensation method and characteristic must be taken from the model-specific documentation.

2.7 Distance Protection (ANSI 21)

Distance protection measures the apparent impedance between the relay location and the fault.

The basic relationship is:

\[ Z=\frac{V}{I} \]

Typical settings include:

  • Zone 1 reach.
  • Zone 2 reach.
  • Zone 3 reach.
  • Zone operating times.
  • Resistive reach.
  • Directional characteristics.
  • Power swing blocking.
  • Load encroachment.
  • Teleprotection logic.

Setting calculations must consider line impedance, adjacent line sections, remote infeed, fault resistance and network operating conditions.

2.8 Verification of Protection Settings

Every setting should be verified using:

  1. Approved protection calculations.
  2. Equipment nameplate data.
  3. CT and VT ratios.
  4. Network fault studies.
  5. Coordination studies.
  6. Relay setting reports.
  7. Independent engineering review.
  8. Secondary injection tests.

Protection setting verification should include both numerical values and functional logic.

3. Setting Group Management

3.1 What Are Setting Groups?

Setting groups allow a protection relay to operate with different protection settings under different network conditions.

For example, a feeder relay may require different settings depending on whether:

  • The network operates in parallel.
  • One transformer is out of service.
  • The system operates in an alternative configuration.
  • A particular busbar arrangement is selected.

The relay can store multiple setting groups, where supported.

3.2 Typical Setting Group Applications

Operating conditionPossible setting requirement
Normal network operationNormal protection settings
Alternative network configurationModified coordination
Transformer parallel operationRevised fault level assumptions
Generator connectedDifferent directional conditions
Maintenance configurationApproved alternative protection arrangement

3.3 Setting Group Changeover

Setting group selection may be controlled through:

  • Local operator command.
  • Binary input.
  • SCADA command.
  • Communication service.
  • Internal relay logic.

The available selection methods depend on the NARI relay.

3.4 Setting Group Testing

During commissioning, verify:

  1. All required groups are available.
  2. Each group contains the approved settings.
  3. The correct group is active.
  4. The selection method operates correctly.
  5. Group changeover is indicated.
  6. Protection functions respond according to the active group.
  7. The active group is correctly reported to SCADA, where configured.

An incorrect setting group can compromise protection coordination even if individual setting values are correct.

4. Binary Input and Output Testing

4.1 Introduction to Binary Inputs and Outputs

Binary inputs and outputs are essential interfaces between protection relays, circuit breakers, auxiliary relays, control panels and substation automation systems.

A binary input receives a digital signal from external equipment.

A binary output sends a control or indication signal to external equipment.

NARI protection relays use binary I/O for functions such as:

  • Circuit breaker position monitoring.
  • Disconnector status monitoring.
  • Protection blocking.
  • External trip initiation.
  • Circuit breaker failure initiation.
  • Trip circuit supervision.
  • Protection alarm indication.
  • Remote control.
  • Interlocking.
  • External protection signals.

4.2 Binary Input Applications

Typical binary inputs include:

Binary inputTypical application
BI1Circuit breaker closed
BI2Circuit breaker open
BI3External protection trip
BI4Protection blocking
BI5Breaker failure initiation
BI6Local/remote selection
BI7External alarm
BI8Circuit breaker spring charged

These assignments are illustrative. Actual assignments depend on the relay configuration and project wiring diagrams.

4.3 Binary Output Applications

Typical binary outputs include:

Binary outputTypical application
BO1Circuit breaker trip
BO2Circuit breaker close
BO3Protection alarm
BO4Protection start
BO5Breaker failure output
BO6External blocking
BO7General relay alarm

4.4 Binary Input Testing Procedure

The following procedure can be used during relay testing:

  1. Review the approved binary input assignment.
  2. Identify the corresponding terminal numbers.
  3. Verify the external wiring.
  4. Confirm the rated input voltage.
  5. Isolate external circuits where required by the approved test procedure.
  6. Apply the appropriate test voltage using a suitable test source.
  7. Monitor the input status on the relay.
  8. Verify the corresponding internal logic.
  9. Confirm event recording.
  10. Restore the circuit and verify normal status.

4.5 Binary Output Testing Procedure

Binary output testing verifies that the relay operates the correct physical output when the corresponding protection or control condition occurs.

The procedure includes:

  1. Review the binary output matrix.
  2. Identify the output relay contacts.
  3. Verify terminal numbers.
  4. Check normally open and normally closed contact arrangements.
  5. Apply a controlled test condition.
  6. Monitor the output contact using suitable test equipment.
  7. Verify the associated external signal, where appropriate.
  8. Confirm event recording.
  9. Restore all circuits.

4.6 Binary I/O Test Matrix

Test itemExpected result
BI1 activationCorrect input indication
BI2 activationCorrect input indication
External trip inputCorrect trip logic response
Blocking inputCorrect blocking response
Local/remote inputCorrect control mode
Protection trip outputCorrect output contact
Alarm outputCorrect alarm contact
Breaker close outputCorrect close command contact
Output resetCorrect return to normal

4.7 Important Engineering Considerations

During binary I/O testing, check:

  • DC supply voltage.
  • Input threshold.
  • Input polarity.
  • Contact wetting arrangements.
  • Contact ratings.
  • Contact bounce.
  • Input debounce settings, where available.
  • Output contact isolation.
  • Interposing relay requirements.
  • External circuit supervision.

Never apply an assumed voltage to a binary input without checking its rated operating range.

5. CT and VT Circuit Verification

5.1 Importance of CT and VT Verification

Current transformers and voltage transformers provide the electrical signals used by protection relays.

Incorrect CT or VT connections can cause:

  • Incorrect current measurements.
  • Incorrect voltage measurements.
  • Differential protection maloperation.
  • Incorrect directional protection operation.
  • Distance protection errors.
  • Incorrect residual current measurement.
  • Unwanted protection trips.

CT and VT verification is therefore a critical commissioning activity.

5.2 CT Circuit Verification

Before energizing a protection system, verify:

  • CT ratio.
  • CT secondary rating.
  • CT polarity.
  • Phase identification.
  • Core allocation.
  • Terminal connections.
  • CT secondary earthing.
  • Secondary circuit continuity.
  • Shorting terminal arrangements.
  • Burden and circuit suitability.

5.3 CT Ratio Verification

Consider a CT with a ratio of:

\[ 600/1A \]

When the primary current is 300 A, the expected secondary current is:

\[ I_s=\frac{300}{600}=0.5A \]

The measured relay current should correspond to the expected value, allowing for test equipment accuracy and circuit conditions.

5.4 CT Polarity Verification

CT polarity is important for directional and differential protection.

The polarity markings P1/P2 and S1/S2 define the intended relationship between primary and secondary current directions.

Incorrect polarity can cause differential current to appear during normal load or external faults.

Polarity should be verified using an appropriate test method and the approved wiring drawings.

5.5 CT Phase Identification

Verify the phase sequence and phase assignment.

For example:

Primary phaseRelay current input
Phase AIA
Phase BIB
Phase CIC
Neutral or residualIN, where applicable

The actual terminal designations must be taken from the relay wiring diagram.

5.6 CT Secondary Earthing

CT secondary circuits should be earthed at the designated point in accordance with the project design and applicable standards.

Multiple unintended earth connections can create circulating currents and measurement errors.

Important safety requirement: Never open-circuit an energized CT secondary circuit. Before disconnecting or testing CT circuits, use approved shorting arrangements and follow the site’s isolation and safety procedures.

5.7 VT Circuit Verification

VT circuit verification should include:

  • Primary-to-secondary ratio.
  • Phase identification.
  • Phase sequence.
  • Polarity.
  • Neutral connection.
  • Fuse and MCB arrangements.
  • Secondary earthing.
  • Voltage circuit continuity.
  • Relay voltage input mapping.

5.8 VT Ratio Example

Consider a voltage transformer:

\[ 132kV/110V \]

The ratio is:

\[ CTR_V=\frac{132000}{110}=1200 \]

If the primary voltage is 66 kV, the expected secondary voltage is:

\[ V_s=\frac{66000}{1200}=55V \]

The relay voltage measurement should correspond to the expected secondary voltage, considering the configured voltage ratio and connection arrangement.

5.9 Phase Sequence Verification

A three-phase voltage system should have the correct phase sequence.

Incorrect phase sequence can affect:

  • Directional overcurrent protection.
  • Distance protection.
  • Power measurement.
  • Synchronism check.
  • Directional earth fault protection.

5.10 CT/VT Verification Checklist

CheckExpected result
CT ratioMatches approved design
CT polarityCorrect
CT phase identificationCorrect
CT secondary continuitySatisfactory
CT earthingCorrect designated point
VT ratioMatches approved design
VT polarityCorrect
VT phase sequenceCorrect
VT fusesCorrect rating and condition
Relay measurementCorrect magnitude and phase

6. Secondary Injection Testing

6.1 What Is Secondary Injection Testing?

Secondary injection testing is a method of testing protection relays by injecting simulated current and voltage signals directly into their secondary measurement inputs.

It allows engineers to verify the relay’s measurement accuracy, protection pickup values, operating times and logic behavior without injecting primary current into the power system.

Common test equipment includes:

  • OMICRON CMC test sets.
  • OMICRON Test Universe.
  • Other compatible secondary injection systems.

6.2 Objectives of Secondary Injection

Secondary injection tests can verify:

  • Current measurement.
  • Voltage measurement.
  • Frequency measurement.
  • Phase angle measurement.
  • Protection pickup.
  • Protection operating time.
  • Protection reset.
  • Directional characteristics.
  • Differential characteristics.
  • Distance protection zones.
  • Binary input response.
  • Binary output response.

6.3 Test Equipment Connections

A typical secondary injection test arrangement includes:

       OMICRON CMC TEST SET
                |
         Current Outputs
                |
         Voltage Outputs
                |
                v
         NARI PROTECTION
              RELAY
                |
       +--------+--------+
       |                 |
   Binary Inputs    Binary Outputs
       |                 |
       +--------+--------+
                |
          Test Software

The exact test connections depend on the relay input configuration and the selected test equipment.

6.4 Current Measurement Test

For a three-phase overcurrent relay, inject balanced three-phase currents.

Example:

PhaseInjected current
IA1.00 A
IB1.00 A
IC1.00 A

Verify that the relay displays the correct phase currents.

Repeat the test at several current levels.

6.5 Voltage Measurement Test

Inject balanced three-phase voltages according to the relay’s nominal secondary voltage and configured measurement convention.

Verify:

  • Phase voltage.
  • Line voltage.
  • Voltage magnitude.
  • Phase angle.
  • Frequency.

6.6 Phase Angle Verification

Inject three-phase voltage and current signals with known phase angles.

For a balanced system with positive phase sequence, the voltage angles can be represented as:

\[ V_A=0^\circ \]

\[ V_B=-120^\circ \]

\[ V_C=120^\circ \]

The corresponding current angles should be set according to the required power factor and test objective.

Check that the relay displays the expected phase relationships.

6.7 Operating Time Testing

For a protection function, increase the injected current above the pickup value and measure the time between the start of the test condition and the relay trip output.

Compare the measured operating time against the expected characteristic and permitted tolerance.

6.8 Secondary Injection Test Report

A typical test record includes:

Test parameterRecorded information
Relay modelActual NARI model
Serial numberDevice identification
FirmwareInstalled version
Test equipmentManufacturer and model
Test currentInjected value
Test voltageInjected value
Pickup valueMeasured result
Operating timeMeasured result
Output statusPass/fail
Test dateDate of testing
EngineerResponsible person

6.9 Important Testing Precautions

  • Use the correct test plug and terminal arrangement.
  • Confirm relay input ratings.
  • Prevent unintended circuit breaker operation.
  • Isolate trip outputs where required.
  • Verify CT and VT isolation arrangements.
  • Check the active setting group.
  • Record the original relay configuration.
  • Restore all test connections after testing.

7. Protection Function Testing

Protection function testing verifies that each protection element operates according to its approved settings and operating characteristics.

The test engineer should select test methods appropriate to the specific NARI relay and protection application.

7.1 Overcurrent Protection Testing (50/51)

The test should verify:

  • Pickup current.
  • Reset behavior.
  • Operating time.
  • Inverse-time characteristic.
  • High-set operation.
  • Directional supervision, where applicable.
  • Trip output.

Example test matrix:

Test currentExpected result
Below pickupNo operation
Near pickupPickup at specified threshold
Above pickupProtection operates
High currentHigh-set function responds, if configured

For inverse-time testing, use multiple current points and compare measured times with the configured curve.

7.2 Earth Fault Protection Testing (50N/51N)

Verify:

  • Residual current measurement.
  • Pickup threshold.
  • Time delay.
  • Directional supervision, where applicable.
  • Trip output.
  • Blocking conditions.

The test must reproduce the intended residual or neutral current input arrangement.

7.3 Directional Overcurrent Testing (67)

Directional overcurrent testing verifies both current magnitude and directional decision.

The test should include:

  • Forward fault condition.
  • Reverse fault condition.
  • Polarizing voltage.
  • Current phase angle.
  • Pickup current.
  • Operating time.
  • Directional blocking.

7.4 Differential Protection Testing (87)

Differential protection testing is particularly important for transformer, generator and line protection.

Verify:

  • Differential pickup.
  • Restraint characteristic.
  • Bias slope.
  • High-set differential operation.
  • External fault stability.
  • CT ratio compensation.
  • Phase compensation.
  • Trip output.

For transformer differential protection, additional tests may include:

  • Vector group compensation.
  • Zero-sequence elimination.
  • Magnetizing inrush restraint.
  • Overexcitation restraint, where applicable.

7.5 Distance Protection Testing (21)

Distance protection testing verifies the relay’s impedance measurement and operating zones.

Typical tests include:

  • Zone 1 reach.
  • Zone 2 reach.
  • Zone 3 reach.
  • Resistive reach.
  • Forward direction.
  • Reverse direction.
  • Operating time.
  • Load encroachment.
  • Power swing blocking, where configured.

A distance relay test set can simulate voltage and current conditions corresponding to specific impedance points.

7.6 Under/Overvoltage Testing (27/59)

Verify:

  • Pickup voltage.
  • Dropout voltage.
  • Operating time.
  • Voltage phase selection.
  • Blocking conditions.
  • Alarm and trip outputs.

7.7 Frequency Protection Testing (81)

Verify:

  • Underfrequency pickup.
  • Overfrequency pickup.
  • Time delay.
  • Frequency measurement accuracy.
  • Stage coordination.
  • Blocking conditions.

7.8 Breaker Failure Protection Testing (50BF)

Breaker failure protection should be tested according to the approved breaker failure philosophy.

Typical checks include:

  • Breaker failure initiation.
  • Current supervision.
  • Breaker auxiliary contact supervision.
  • Time delay.
  • Retrip logic.
  • Backup trip output.

7.9 Protection Function Test Matrix

Protection functionMain test
50/51Pickup and operating time
50N/51NResidual current response
67Directional characteristic
21Impedance zones
87Differential characteristic
27Undervoltage pickup
59Overvoltage pickup
81Frequency response
50BFBreaker failure logic
49Thermal characteristic
46Negative-sequence response
32Directional power response
40Loss-of-excitation characteristic

Only functions actually implemented and enabled in the selected NARI relay should be included in the test plan.

8. Trip Circuit Verification

8.1 Introduction

The trip circuit is responsible for transferring the protection relay’s trip command to the circuit breaker trip coil.

A protection relay may detect a fault correctly, but if the trip circuit is defective, the circuit breaker may fail to open.

Therefore, trip circuit verification is a critical commissioning activity.

8.2 Typical Trip Circuit Architecture

       NARI PROTECTION RELAY
                |
           Trip Output
                |
          Interposing
             Relay
                |
          Trip Circuit
                |
          Circuit Breaker
                |
           Trip Coil 1

A second trip circuit may be provided where required by the protection and switchgear design.

8.3 Trip Circuit Components

Typical components include:

  • Protection relay trip contact.
  • Auxiliary trip relay.
  • Trip circuit fuse or MCB.
  • Trip coil.
  • Circuit breaker auxiliary contacts.
  • Trip circuit supervision relay.
  • DC supply.
  • Terminal blocks and wiring.

8.4 Trip Circuit Checks

Verify:

  1. Correct DC supply.
  2. Correct trip coil voltage rating.
  3. Correct trip relay output contact.
  4. Correct interposing relay connections.
  5. Correct circuit breaker trip coil connections.
  6. Auxiliary contact operation.
  7. Trip circuit supervision.
  8. Correct alarm generation.
  9. Correct trip indication.
  10. Correct breaker position feedback.

8.5 Trip Circuit Supervision

Trip Circuit Supervision (TCS) monitors the integrity of the trip circuit.

It can detect conditions such as:

  • Loss of DC supply.
  • Open trip circuit.
  • Trip coil circuit interruption.
  • Blown fuse.
  • Wiring failure.

The exact supervision method depends on the circuit design and relay implementation.

8.6 Trip Circuit Functional Testing

Under an approved commissioning procedure:

  • Verify the trip circuit wiring.
  • Check the supervision indication.
  • Simulate appropriate supervision faults.
  • Verify the corresponding alarm.
  • Restore the normal circuit.
  • Perform a controlled trip test.
  • Confirm breaker operation.
  • Verify breaker auxiliary feedback.

8.7 Trip Circuit Test Matrix

TestExpected result
Normal DC supplyHealthy indication
Trip circuit interruptionTCS alarm
Trip commandCorrect trip contact
Trip coil energizationBreaker operates
Breaker open feedbackCorrect indication
Trip resetCorrect return to normal

Actual circuit interruption tests must be planned to avoid unintended operation and must follow the manufacturer’s test procedure.

9. GOOSE Testing

9.1 Introduction

GOOSE is an IEC 61850 communication service used for fast exchange of event information between IEDs.

In NARI-based digital substations, GOOSE can be used for:

  • Protection trip signals.
  • Breaker status.
  • Interlocking.
  • Blocking.
  • Breaker failure signals.
  • Busbar protection signals.
  • Transfer trip.
  • Other configured binary and status information.

9.2 GOOSE Test Objectives

The commissioning engineer should verify:

  • Publisher configuration.
  • Subscriber configuration.
  • Dataset correctness.
  • GOOSE control block.
  • Destination multicast MAC.
  • APPID.
  • VLAN ID.
  • VLAN priority.
  • Configuration revision.
  • Signal value.
  • Signal quality.
  • Subscriber application response.

9.3 GOOSE Test Architecture

       NARI IED - BAY 1
               |
         GOOSE Publisher
               |
         Ethernet Network
               |
         GOOSE Subscriber
               |
       NARI IED - BAY 2
               |
         Application Logic
               |
         Expected Response

9.4 GOOSE Testing with IEDScout

IEDScout can be used, subject to the supported features and device configuration, to inspect IEC 61850 data models and GOOSE communication.

A typical test includes:

  1. Connect the engineering workstation to the station network.
  2. Identify the GOOSE publisher.
  3. Verify the dataset.
  4. Inspect the GOOSE control block.
  5. Monitor the transmitted signal.
  6. Trigger a controlled change.
  7. Verify the received information.
  8. Check signal quality.
  9. Verify the application response.

9.5 GOOSE Testing with Wireshark

Wireshark can capture and decode GOOSE traffic.

Useful display filters include:

goose

For MMS communication:

tcp.port == 102

During analysis, verify:

  • Source MAC address.
  • Destination MAC address.
  • APPID.
  • VLAN ID.
  • gocbRef.
  • datSet.
  • stNum.
  • sqNum.
  • confRev.
  • timeAllowedToLive.
  • Dataset values.

9.6 GOOSE Failure Testing

A complete commissioning plan should also consider communication failure.

Tests may include:

  • Publisher communication loss.
  • Network path interruption.
  • Subscriber communication supervision.
  • Invalid quality.
  • Test mode.
  • Recovery after communication restoration.

The expected fail-safe response must be defined in the approved protection and control design.

9.7 GOOSE Test Report

Record:

ParameterResult
Publisher IEDIdentified
Subscriber IEDIdentified
DatasetVerified
APPIDVerified
VLANVerified
Multicast MACVerified
Signal valueVerified
QualityVerified
Subscriber responseVerified
Communication failure responseVerified

10. End-to-End Protection Testing

10.1 What Is End-to-End Testing?

End-to-end protection testing verifies the complete protection system from the measurement inputs to the final circuit breaker operation.

Unlike an individual relay test, end-to-end testing examines the interaction between multiple devices and protection system components.

It is particularly important for:

  • Transmission line protection.
  • Line differential protection.
  • Transformer differential protection.
  • Busbar protection.
  • Teleprotection schemes.
  • GOOSE-based protection systems.
  • Interconnected protection and control systems.

10.2 Typical End-to-End Test Architecture

For a transmission line with protection relays at both terminals:

         SUBSTATION A
              |
        OMICRON CMC A
              |
        NARI RELAY A
              |
        Communication
           Channel
              |
        NARI RELAY B
              |
        OMICRON CMC B
              |
         SUBSTATION B

The two test systems simulate electrical conditions at both ends of the protected circuit.

10.3 Line Differential Protection Testing

For line differential protection, the test verifies that the protection relays at both ends correctly compare the measured currents.

Typical tests include:

  • Normal load current.
  • External fault.
  • Internal fault.
  • Differential pickup.
  • Differential restraint.
  • CT polarity verification.
  • Communication channel interruption.
  • Communication channel restoration.
  • Trip output at both terminals.

For an internal fault, the protection system should operate according to the approved differential protection characteristic.

For an external fault, the protection should remain stable within its specified operating limits.

10.4 Distance Protection with Teleprotection

For transmission line distance protection, end-to-end tests may verify:

  • Zone 1 operation.
  • Zone 2 operation.
  • Zone 3 operation.
  • Permissive overreach transfer trip.
  • Permissive underreach transfer trip.
  • Blocking schemes.
  • Direct transfer trip.
  • Communication channel failure.

The test engineer must confirm the actual teleprotection scheme implemented in the project.

10.5 GOOSE-Based End-to-End Testing

For digital substations, end-to-end testing can verify the complete GOOSE signal chain.

Example:

  1. Simulate a protection pickup in Bay 1.
  2. Verify the internal relay signal.
  3. Confirm GOOSE publication.
  4. Verify network transmission.
  5. Confirm GOOSE reception in Bay 2.
  6. Verify the receiving logic.
  7. Confirm the intended output or blocking action.
  8. Record event timestamps.

10.6 End-to-End Test Matrix

Test scenarioExpected response
Normal loadNo unwanted operation
Internal faultCorrect protection operation
External faultProtection stability
Communication interruptionDefined backup or fail-safe response
Communication restorationNormal operation restored
GOOSE tripCorrect receiving response
Teleprotection commandCorrect remote response
Breaker failureCorrect backup action

10.7 Important Commissioning Considerations

End-to-end testing must be planned carefully.

The test team should:

  • Coordinate both substations.
  • Verify communication channel availability.
  • Confirm protection settings at both terminals.
  • Check test equipment synchronization.
  • Verify current polarity and phase reference.
  • Isolate actual trip circuits where required.
  • Confirm test and normal operating modes.
  • Record all test results.

For differential protection, current direction and reference conventions must be checked carefully. Incorrect test connections can produce misleading results.

11. Fault Record Analysis

11.1 Introduction

Fault record analysis is an essential activity following protection relay operation and during commissioning.

Modern protection relays record information about faults, protection element operation, measured quantities and trip events.

This information helps engineers understand why a relay operated and whether the protection system behaved correctly.

NARI relay recording capabilities and supported file formats depend on the individual model.

11.2 Types of Relay Records

Typical records include:

Event Records

Event records may contain:

  • Protection element pickup.
  • Protection trip.
  • Breaker open.
  • Breaker close.
  • Binary input changes.
  • Binary output operation.
  • Communication alarms.
  • Setting group changes.

Disturbance Records

Disturbance records may contain sampled electrical quantities such as:

  • Phase currents.
  • Phase voltages.
  • Residual current.
  • Frequency.
  • Digital status signals.
  • Protection element signals.

Fault Records

Fault records may include calculated values such as:

  • Fault current.
  • Fault voltage.
  • Fault impedance.
  • Fault type.
  • Fault direction.
  • Protection zone.
  • Fault duration.

The exact contents depend on the relay model and recording configuration.

11.3 COMTRADE Records

COMTRADE is a standard format for exchanging transient data records from power system protection and measurement equipment.

The relevant standard is IEC 60255-24.

Common COMTRADE file components include:

File extensionPurpose
.CFGConfiguration information
.DATRecorded sample data
.HDROptional descriptive information
.INFOptional additional information

The availability of COMTRADE export should be confirmed for the specific NARI relay.

11.4 Fault Record Analysis Workflow

A practical analysis process includes:

  1. Retrieve the fault record from the relay.
  2. Identify the fault date and time.
  3. Determine the protection function that operated.
  4. Examine phase current waveforms.
  5. Examine phase voltage waveforms.
  6. Check residual and negative-sequence quantities.
  7. Identify the fault type.
  8. Examine protection pickup and trip signals.
  9. Verify circuit breaker operation.
  10. Compare the actual operation with the approved settings.
  11. Determine whether the operation was correct.
  12. Prepare an engineering report.

11.5 Fault Type Identification

Different faults produce different current and voltage patterns.

Fault typeTypical characteristics
Phase A to earthHigh phase A and residual current
Phase B to earthHigh phase B and residual current
Phase C to earthHigh phase C and residual current
Phase A to BHigh currents in phases A and B
Phase B to CHigh currents in phases B and C
Phase C to AHigh currents in phases C and A
Three-phase faultHigh balanced or near-balanced phase currents

These are simplified characteristics. Actual waveforms depend on fault location, system grounding, fault impedance, network configuration and CT behavior.

11.6 Example: Overcurrent Protection Operation

Consider a feeder relay with:

  • CT ratio: 600/1 A.
  • Phase overcurrent pickup: 0.8 A secondary.
  • Measured fault current: 720 A primary.

The equivalent secondary current is:

\[ I_s=\frac{720}{600}=1.2A \]

The operating current is:

\[ \frac{1.2}{0.8}=1.5 \]

Therefore, the measured current is 1.5 times the configured pickup.

The engineer should compare the recorded operating time with the expected time-current characteristic.

11.7 Waveform Analysis

Waveform analysis should examine:

  • Fault inception.
  • Current magnitude.
  • Voltage collapse.
  • DC offset.
  • Harmonic content.
  • CT saturation.
  • Protection pickup.
  • Trip command.
  • Circuit breaker opening.
  • Fault clearance.

11.8 Sequence-of-Events Analysis

Sequence-of-events records are particularly useful for identifying the order of protection and switching operations.

For example:

EventIllustrative time
Overcurrent pickup10:15:20.100
Protection trip10:15:20.450
Breaker trip command10:15:20.455
Breaker open indication10:15:20.520

The time differences can help engineers assess protection operation and breaker response.

Accurate time synchronization is essential when comparing events from multiple IEDs.

11.9 Common Fault Analysis Problems

ProblemPossible cause
Incorrect current waveformCT polarity or ratio issue
Incorrect voltage waveformVT wiring or ratio issue
Unexpected differential currentCT compensation or wiring error
Incorrect directional decisionPhase sequence or polarization problem
Missing trip recordRecording configuration
Incorrect event sequenceTime synchronization issue
Distorted fault currentCT saturation or actual fault characteristics
Unexpected protection tripSettings or logic problem

11.10 Engineering Tools

Useful tools for fault record analysis include:

  • NARI-supported relay software.
  • SIGRA, where the exported record format is supported.
  • OMICRON Test Universe.
  • COMTRADE analysis software.
  • Wireshark for communication event correlation.
  • Spreadsheet tools for calculations and comparisons.

Engineers should confirm file-format compatibility before selecting an analysis application.

12. Commissioning Checklist and Test Reports

12.1 Introduction

A complete commissioning process should produce documented evidence that the NARI protection system has been configured, tested and verified according to the project requirements.

The test report should identify the equipment, test procedure, test conditions, measured results, acceptance criteria and any outstanding issues.

12.2 Relay Identification

Every test report should include:

InformationDescription
ManufacturerNARI / NR Electric
Relay modelActual device model
Serial numberDevice serial number
FirmwareInstalled firmware
Bay nameProtected equipment
Voltage levelSystem voltage
CT ratioConfigured ratio
VT ratioConfigured ratio
Frequency50 Hz or 60 Hz
Setting groupActive group
Setting fileApproved revision
Test dateDate of testing
Test engineerResponsible person

12.3 Recommended Test Report Structure

A professional relay testing report should include:

  1. Project identification.
  2. Equipment identification.
  3. Applicable drawings.
  4. Approved protection settings.
  5. Test equipment details.
  6. Calibration information.
  7. Test procedure.
  8. Test connections.
  9. Test results.
  10. Acceptance criteria.
  11. Deviations and corrective actions.
  12. Final assessment.
  13. Engineer and client approval.

12.4 Protection Relay Test Matrix

Test categoryMain verification
Visual inspectionPhysical condition
ConfigurationCorrect relay settings
CT circuitsRatio, polarity and continuity
VT circuitsRatio, polarity and phase sequence
Binary inputsCorrect input operation
Binary outputsCorrect contact operation
MeasurementsCurrent and voltage accuracy
OvercurrentPickup and time
Earth faultPickup and time
Directional protectionDirectional characteristic
DifferentialBias and differential operation
DistanceImpedance zones
Voltage protectionPickup and time
Frequency protectionFrequency thresholds
Trip circuitComplete trip path
GOOSEPublisher/subscriber operation
MMSMonitoring and reporting
End-to-endComplete protection scheme
Fault recordsRecord retrieval and analysis

12.5 Final Commissioning Checklist

NARI relay testing and commissioning checklist

Interactive engineering checklist

Test completion

0/27

Relay model and firmware verifiedOriginal setting file backed upApproved setting calculations reviewedActive setting group verifiedCT ratio and polarity verifiedVT ratio and phase sequence verifiedCT and VT secondary wiring checkedBinary input tests completedBinary output tests completedCurrent measurement testedVoltage measurement testedOvercurrent protection testedEarth fault protection testedDirectional protection tested, if applicableDifferential protection tested, if applicableDistance protection tested, if applicableOther enabled protection functions testedTrip circuit supervision verifiedCircuit breaker trip circuit testedGOOSE publisher and subscriber testedMMS communication testedEnd-to-end protection tested, if applicableFault and event records retrievedFinal relay settings comparedAll test connections restoredFinal commissioning report approvedAs-built configuration backed up

Reset checklist

12.6 Acceptance Criteria

Each test should be assessed against the applicable acceptance criteria.

These may include:

  • Manufacturer specifications.
  • Approved protection settings.
  • Project technical requirements.
  • Applicable IEC standards.
  • Approved testing procedures.
  • Relay accuracy specifications.
  • Protection coordination requirements.

A test should not be declared successful merely because the relay displays an expected value. Its functional response and the complete associated signal path must also be verified where required.

12.7 Restoration After Testing

Before returning the protection system to service, verify:

  • All test plugs removed.
  • All temporary test connections removed.
  • CT shorting arrangements restored correctly.
  • VT fuses and MCBs restored.
  • Trip circuits restored.
  • Binary inputs and outputs restored.
  • GOOSE and MMS configurations restored.
  • Correct setting group selected.
  • Correct protection functions enabled.
  • All temporary blocks removed.
  • Relay alarms cleared.
  • Final configuration backed up.
  • Operational authorization obtained.

The final restoration check is essential to prevent protection systems being left in an incomplete or test condition.

13. Best Practices for NARI Relay Testing and Commissioning

Successful commissioning requires coordination between protection engineers, commissioning engineers, control engineers and substation operators.

The following practices are recommended.

13.1 Always Verify the Approved Settings

Do not rely only on the settings already stored in the relay.

Compare the actual configuration against the approved setting calculation and revision.

13.2 Test the Complete Protection Chain

Testing should cover the complete path:

CT / VT
   |
   v
Protection Relay
   |
   v
Protection Logic
   |
   v
Trip Output
   |
   v
Trip Circuit
   |
   v
Circuit Breaker
   |
   v
Breaker Feedback
   |
   v
SCADA / Event Recording

13.3 Maintain Test Records

Record all test results, including:

  • Injected values.
  • Measured values.
  • Pickup thresholds.
  • Operating times.
  • Binary input states.
  • Binary output states.
  • Communication results.
  • Deviations.
  • Corrective actions.

13.4 Use Appropriate Test Equipment

Select test equipment according to the protection function and required test accuracy.

For example:

  • Secondary injection test sets for current and voltage protection tests.
  • Binary I/O test equipment for control circuit verification.
  • Network analyzers for IEC 61850 communication.
  • Suitable primary injection equipment for CT circuit tests, where required.
  • End-to-end test systems for line differential and teleprotection applications.

13.5 Understand the Protection Philosophy

A relay can pass an individual injection test and still be incorrectly integrated into the overall protection system.

Engineers must understand:

  • Protection zones.
  • Main and backup protection.
  • Trip matrices.
  • Interlocking.
  • Blocking logic.
  • Breaker failure logic.
  • Communication failure behavior.
  • System restoration philosophy.

13.6 Maintain Configuration Control

Every setting modification should have:

  • An approved change request.
  • A revision number.
  • An engineering justification.
  • A backup of the previous configuration.
  • A verification record.
  • Final approval.

14. Applicable IEC Standards and Technical References

The following standards are relevant to NARI protection relay settings, testing and commissioning.

StandardEngineering subject
IEC 60255 seriesMeasuring relays and protection equipment
IEC 60255-1Common requirements
IEC 60255-24COMTRADE transient data exchange
IEC 61850 seriesSubstation communication and automation
IEC 61850-6SCL engineering
IEC 61850-8-1MMS and Ethernet mapping
IEC 61850-10Conformance testing
IEC 61869 seriesInstrument transformers
IEC 60044 seriesLegacy instrument transformer standards
IEC 60870-5-103Protection equipment communication
IEC 60870-5-104Telecontrol communication
IEC 62439-3PRP and HSR network redundancy
IEC 62351Power system communication security

Additional references should include:

  • NARI protection relay user manuals.
  • NARI communication manuals.
  • NARI engineering software documentation.
  • Approved protection setting calculations.
  • CT and VT test reports.
  • Circuit breaker manufacturer’s documentation.
  • Approved single-line diagrams.
  • Protection coordination studies.
  • Project commissioning specifications.

The applicable editions and project-specific requirements should always be checked.

15. NARI Protection Relay Testing and Commissioning Training by Elec-Engg

Protection Relay Testing – OMICRON

Practical relay testing and commissioning require more than understanding protection functions and reading relay manuals.

Engineers must be able to calculate settings, configure protection devices, perform secondary injection tests, verify binary circuits, analyze fault records and validate the complete protection system.

Elec-Engg provides practical training in power system protection, relay engineering, protection testing and substation automation by Dr Saeed Roostaee / Elec-Engg.

Relevant training subjects include:

  • Protection relay fundamentals.
  • Protection setting calculations.
  • Overcurrent and earth fault protection.
  • Directional overcurrent protection.
  • Transformer differential protection.
  • Generator protection.
  • Distance protection.
  • CT and VT circuit engineering.
  • Secondary injection using OMICRON CMC.
  • OMICRON Test Universe.
  • Binary input and output testing.
  • Trip circuit verification.
  • Protection coordination.
  • IEC 61850 communication.
  • GOOSE testing.
  • IEDScout and Wireshark.
  • End-to-end protection testing.
  • COMTRADE and fault record analysis.
  • Protection relay commissioning documentation.

Training is available through structured online learning, recorded technical courses, live online sessions and customized face-to-face or in-house training.

For NARI-specific training programs, exercises can be adapted to the actual relay models, available engineering software, firmware versions and technical documentation supplied by the organization.

Explore Elec-Engg training:

  • Elec-Engg — Power System Protection and Substation Automation
  • Substation Automation Training
  • Structured Self-Paced Training
  • Pre-Recorded Video Training

16. Conclusion

NARI protection relay settings, testing and commissioning are essential activities for ensuring the reliability, selectivity and operational performance of electrical protection systems.

Successful commissioning requires a systematic approach covering the complete protection chain, from instrument transformer circuits and relay settings to trip circuits, communication systems and circuit breaker operation.

The most important engineering activities include:

  1. Understanding NARI relay setting files and configuration.
  2. Calculating and verifying protection settings.
  3. Managing setting groups.
  4. Testing binary inputs and outputs.
  5. Verifying CT and VT circuits.
  6. Performing secondary injection testing.
  7. Testing individual protection functions.
  8. Verifying trip circuits.
  9. Testing IEC 61850 GOOSE communication.
  10. Performing end-to-end protection tests.
  11. Analyzing fault and disturbance records.
  12. Preparing complete commissioning checklists and test reports.

Engineers who combine protection theory, setting calculations, practical testing and communication engineering can commission and maintain NARI protection systems more effectively.

A properly commissioned protection system is not simply a relay that passes an injection test. It is a complete, verified protection chain that detects faults, makes the correct protection decision, operates the intended circuit breaker and provides reliable event information for system operation and fault investigation.