- Introduction
- 1. Understanding the SAS Engineering Scope
- 2. Collecting Engineering Documents
- 3. Preparing the IED List
- 4. Developing the SAS Architecture
- 5. Communication Network Engineering
- 6. GE Multilin Relay Configuration
- 7. IEC 61850 Engineering
- 8. SCL File Engineering
- 9. HMI Engineering
- 10. SCADA Gateway Engineering
- 11. SAS Engineering Example: Feeder Bay
- 12. Configuration Management and Documentation
- 13. FAT and SAT for GE SAS
- 14. Common Engineering Mistakes
- 15. Training on GE SAS Engineering by Elec-Engg
- Conclusion
- Frequently Asked Questions
- 1. Which software is used for GE SAS engineering?
- 2. Can GE Multilin relays be integrated with third-party IEDs?
- 3. What is the difference between relay configuration and SAS engineering?
- 4. What is an SCD file?
- 5. Is GOOSE required in every SAS?
- 6. What is the purpose of a SCADA gateway?
- 7. What is FAT in SAS projects?
- 8. What is SAT?
- 9. Why is time synchronization important?
- 10. What is the most important SAS engineering document?
- Image
Introduction
Engineering and configuring a Substation Automation System (SAS) requires coordinated work across protection relays, bay control units, station-level systems, communication networks and SCADA interfaces.
In a GE-based substation, engineers may integrate GE Multilin protection relays with bay controllers, station computers, Ethernet switches, gateways and third-party IEC 61850-compatible IEDs.
The engineering process is not limited to configuring individual relays. It involves developing the complete system architecture, defining communication relationships, mapping signals, configuring protection and control logic, implementing interlocking, and verifying that all devices operate together correctly.
This article explains a practical engineering workflow for a GE-based SAS, from project documentation and IED selection to communication configuration, integration testing and commissioning.
1. Understanding the SAS Engineering Scope
Before configuring any device, the engineering team must define the complete scope of the substation automation system.
Typical engineering activities include:
- Reviewing the substation single-line diagram.
- Preparing the SAS architecture.
- Defining the IED list.
- Selecting protection and control devices.
- Developing the communication network design.
- Preparing IP addressing and VLAN plans.
- Defining IEC 61850 data models and signal requirements.
- Configuring GOOSE communication.
- Configuring MMS reporting and control.
- Developing HMI graphics.
- Configuring SCADA gateway databases.
- Defining interlocking and control logic.
- Preparing test procedures.
- Performing factory and site acceptance tests.
The project should have an approved engineering baseline before final device configurations are generated.
2. Collecting Engineering Documents
The first step is to collect the documents required for system engineering.
2.1 Electrical drawings
Important drawings include:
- Single-line diagrams.
- AC schematics.
- DC schematics.
- Protection circuit diagrams.
- Circuit-breaker control diagrams.
- Disconnector and earthing switch control diagrams.
- CT and VT connection diagrams.
- Panel wiring diagrams.
These drawings define the primary equipment and its electrical interfaces with the automation system.
2.2 Protection documents
Protection engineering documents include:
- Protection philosophy.
- Protection coordination study.
- Relay setting calculations.
- Protection function allocation.
- Trip matrix.
- Breaker failure philosophy.
- Autoreclosing philosophy.
- Intertrip requirements.
These documents define which protection signals must be monitored, exchanged and displayed by the SAS.
2.3 Automation documents
Typical automation documents include:
- SAS architecture diagram.
- IED list.
- Communication network diagram.
- IEC 61850 signal list.
- GOOSE matrix.
- SCADA point list.
- HMI graphics specification.
- Control and interlocking philosophy.
- Time synchronization architecture.
- Cybersecurity requirements.
The engineering team should maintain consistency between these documents throughout the project.
3. Preparing the IED List
The IED list identifies the devices that form the SAS.
An illustrative substation IED list could be:
| IED reference | Equipment | Application |
|---|---|---|
| F01-PR | GE Multilin feeder relay | Feeder protection |
| F02-PR | GE Multilin feeder relay | Feeder protection |
| T01-PR | GE Multilin transformer relay | Transformer protection |
| B01-BCU | Bay controller | Bay control |
| BB01-PR | Busbar protection IED | Busbar protection |
| GW01 | SCADA gateway | Remote communication |
| HMI01 | Station HMI | Operator interface |
| ENG01 | Engineering workstation | IED configuration |
These are example identifiers, not specific GE product designations.
For every device, record:
- Manufacturer.
- Model.
- Order code.
- Hardware version.
- Firmware version.
- Communication interfaces.
- Protocol support.
- IP address.
- IEC 61850 support, if applicable.
- Required application functions.
- Engineering software.
- Configuration file revision.
This information is important because different models and firmware versions may support different communication services and engineering features.
4. Developing the SAS Architecture
The architecture diagram should clearly identify the relationships between process equipment, bay-level IEDs and station-level systems.
4.1 Process level
The process level contains primary equipment and its measurement and control interfaces.
Examples include:
- CTs.
- VTs.
- Circuit breakers.
- Disconnectors.
- Earthing switches.
- Transformer equipment.
Signals may be transferred using conventional wiring or supported digital process-bus technology.
4.2 Bay level
The bay level contains protection and control IEDs.
A typical feeder bay may contain:
- Feeder protection relay.
- Bay controller.
- Circuit-breaker interfaces.
- Disconnector status inputs.
- Local control switches.
- Protection trip outputs.
The protection relay performs the required protection functions, while the bay controller may provide additional switching, interlocking and monitoring functions.
4.3 Station level
The station level includes:
- Station HMI.
- SCADA gateway.
- Engineering workstation.
- Station communication equipment.
- Time synchronization system.
The station-level equipment collects information from the bay-level devices and provides operator and remote-control interfaces.
5. Communication Network Engineering
The communication network is a critical part of SAS engineering.
The design must support the expected communication traffic and the required availability.
5.1 IP addressing plan
Prepare an IP addressing table before configuring the IEDs.
Example:
| Device | Example IP address |
|---|---|
| Feeder relay F01 | 192.168.10.11 |
| Feeder relay F02 | 192.168.10.12 |
| Transformer relay T01 | 192.168.10.21 |
| Station gateway | 192.168.10.100 |
| Station HMI | 192.168.10.110 |
| Engineering workstation | 192.168.10.120 |
These addresses are illustrative only. The actual addressing scheme must follow the project’s network design.
The engineering team should also define:
- Subnet masks.
- Default gateways, where required.
- VLAN assignments.
- DNS requirements, where applicable.
- Management network addressing.
- Redundant interface addressing, where supported.
Avoid duplicate IP addresses and maintain an approved address register.
5.2 Ethernet switch configuration
Managed Ethernet switches may require configuration of:
- Port assignments.
- VLAN membership.
- Trunk and access ports.
- Multicast forwarding.
- Quality of Service.
- Port security.
- Network management access.
- Redundancy protocols.
- Link monitoring.
The configuration must match the network architecture and the capabilities of the connected devices.
5.3 Network redundancy
Some SAS projects require redundant communication paths.
Common architectures include:
- PRP – Parallel Redundancy Protocol.
- HSR – High-availability Seamless Redundancy.
- Other project-specific redundant Ethernet arrangements.
PRP and HSR have different network architectures and device requirements. Verify support in the actual IEDs and switches before selecting either solution.
6. GE Multilin Relay Configuration
GE Multilin protection relays are configured using the engineering software appropriate to the selected product family.
EnerVista is used across a number of GE Multilin product families, but the exact software version and available configuration functions depend on the relay model.
Typical configuration activities include:
- Establish communication with the relay.
- Retrieve the existing configuration.
- Verify device identification and firmware.
- Configure CT and VT ratios.
- Configure protection functions.
- Enter calculated protection settings.
- Configure binary inputs and outputs.
- Configure programmable logic, where supported.
- Configure communication parameters.
- Configure IEC 61850 functions, where supported.
- Save and validate the configuration.
- Transfer the approved configuration to the device.
- Perform functional testing.
Always preserve the original configuration and maintain revision control.
6.1 Protection settings
Protection settings must come from approved calculations and coordination studies.
Examples include:
- Phase overcurrent pickup.
- Earth-fault pickup.
- Directional settings.
- Differential protection characteristics.
- Distance protection zones.
- Thermal overload settings.
- Breaker failure timers.
Do not copy settings from another installation without verifying the electrical system, CT/VT ratios, relay characteristics and coordination requirements.
6.2 Binary input and output mapping
Binary inputs receive external signals, while binary outputs operate external equipment or provide indications.
Examples of inputs include:
- Breaker closed.
- Breaker open.
- Local/remote selector.
- Protection trip circuit supervision.
- External blocking.
- Disconnector position.
Examples of outputs include:
- Circuit-breaker trip.
- Circuit-breaker close.
- Alarm.
- Lockout.
- External indication.
Signal mapping must be checked against the wiring diagrams and approved trip matrix.
7. IEC 61850 Engineering
IEC 61850 engineering defines how IED information is structured and communicated.
7.1 Logical devices and logical nodes
IEC 61850 uses a standardized data model.
A logical device contains logical nodes representing particular functions or equipment.
Examples include:
- XCBR – Circuit breaker.
- XSWI – Switch.
- MMXU – Measurement.
- PTOC – Time overcurrent protection.
- PDIS – Distance protection.
- PDIF – Differential protection.
- CSWI – Switch control.
The exact logical nodes implemented by a device depend on its supported IEC 61850 model.
7.2 MMS configuration
MMS is commonly used for client-server communication between IEDs and station-level clients.
Typical engineering activities include:
- Defining the server data model.
- Creating datasets.
- Configuring report control blocks.
- Assigning buffered or unbuffered reporting, where supported.
- Mapping indications and measurements.
- Configuring control models.
- Testing client-server communication.
7.3 GOOSE configuration
GOOSE is used for fast communication between IEDs.
Typical applications include:
- Interlocking.
- Protection blocking.
- Breaker failure initiation.
- Intertrip.
- Equipment status distribution.
The engineering team must define publishers, subscribers, datasets, control blocks and network parameters.
The actual GOOSE configuration workflow depends on the IED’s IEC 61850 implementation and the supported engineering tools.
8. SCL File Engineering
SCL files support structured IEC 61850 system configuration.
The main file types are:
| File | Description |
|---|---|
| ICD | IED Capability Description |
| IID | Instantiated IED Description |
| CID | Configured IED Description |
| SCD | Substation Configuration Description |
| SSD | System Specification Description |
8.1 Import IED descriptions
Obtain the correct manufacturer-provided SCL files for the actual IED models and firmware.
Import the files into the system engineering environment.
8.2 Configure the system
Define:
- IED names.
- Logical devices.
- Communication access points.
- Datasets.
- GOOSE control blocks.
- Reporting configuration.
- External references.
- Network communication parameters.
8.3 Export configured files
Export the required configured IED descriptions and system configuration files using the supported engineering workflow.
8.4 Validate the configuration
Check:
- IED naming consistency.
- Dataset references.
- GOOSE subscriptions.
- Communication parameters.
- External references.
- Configuration revisions.
- Device compatibility.
A valid SCL file does not automatically guarantee correct application logic. Functional testing remains necessary.
9. HMI Engineering
The station HMI is the main local operator interface.
Typical HMI engineering tasks include:
- Creating the substation single-line diagram.
- Adding circuit breakers and disconnectors.
- Mapping equipment status.
- Displaying measurements.
- Configuring alarm lists.
- Configuring event lists.
- Implementing authorized controls.
- Displaying communication health.
- Configuring equipment faceplates.
9.1 Single-line diagram
The single-line diagram should reflect the actual electrical arrangement.
It should clearly indicate:
- Busbar sections.
- Feeder connections.
- Transformer bays.
- Circuit-breaker positions.
- Disconnector positions.
- Earthing switch positions.
9.2 Alarm configuration
Typical alarms include:
- Protection operation.
- Breaker failure.
- Trip circuit supervision.
- Communication failure.
- DC supply failure.
- IED self-supervision alarm.
- Time synchronization failure.
Alarm priorities should follow the utility’s alarm philosophy.
9.3 Control configuration
Control commands must be associated with the correct equipment and subject to the required authorization and interlocking logic.
The HMI must distinguish between a command being issued and equipment confirmation that the operation has actually occurred.
10. SCADA Gateway Engineering
The gateway connects the station automation system to the remote control centre.
Engineering activities include:
- Configuring communication interfaces.
- Defining protocol parameters.
- Mapping indications.
- Mapping measurements.
- Mapping alarms.
- Configuring control points.
- Defining quality information.
- Configuring time tagging.
- Testing communication recovery.
10.1 IEC 60870-5-104 integration
For an IEC 60870-5-104 connection, the engineering team may need to configure:
- Local and remote IP addresses.
- TCP port.
- Common address of ASDU.
- Information object addresses.
- Type identification.
- Cause of transmission.
- General interrogation.
- Time-tagged events.
- Control command behavior.
The exact configuration depends on the gateway implementation and control-centre requirements.
10.2 Point-list verification
The gateway database must be compared against the approved SCADA point list.
For each point, verify:
- Description.
- Source IED.
- Source data reference.
- Destination address.
- Data type.
- Engineering unit.
- Scaling.
- Alarm priority.
- Timestamp behavior.
- Quality handling.
11. SAS Engineering Example: Feeder Bay
Consider a feeder bay containing:
- One circuit breaker.
- Two disconnectors.
- One earthing switch.
- One GE Multilin feeder relay.
- One bay controller.
- Station HMI integration.
A typical engineering sequence is:
Protection engineering
- Configure feeder protection.
- Configure CT and VT ratios.
- Configure trip logic.
- Map breaker status and protection indications.
- Verify protection outputs.
Bay control engineering
- Map breaker and disconnector inputs.
- Configure control outputs.
- Develop interlocking logic.
- Configure local/remote authority.
- Verify switching sequences.
IEC 61850 engineering
- Configure the required data model.
- Define MMS datasets and reports.
- Configure GOOSE signals where required.
- Validate the SCL configuration.
- Test communication.
Station-level engineering
- Add the feeder bay to the HMI.
- Map indications and measurements.
- Configure alarms.
- Configure control commands.
- Integrate points with the gateway.
Commissioning
- Verify wiring.
- Test binary inputs and outputs.
- Test protection.
- Test interlocking.
- Test GOOSE and MMS.
- Test HMI and SCADA.
- Complete end-to-end acceptance tests.
12. Configuration Management and Documentation
SAS configuration management is essential throughout the project lifecycle.
Maintain:
- Original device configurations.
- Approved final configurations.
- Firmware records.
- SCL files.
- Network switch backups.
- Gateway databases.
- HMI project backups.
- Test reports.
- Change records.
- As-built drawings.
Every configuration change should be traceable.
Before changing an operational system, engineers should assess the effect on protection, control, communication and cybersecurity.
13. FAT and SAT for GE SAS
Factory Acceptance Test (FAT)
FAT is performed before delivery or installation to verify the system against the approved project requirements.
Typical FAT activities include:
- IED communication testing.
- Protection logic testing.
- HMI testing.
- Alarm and event testing.
- GOOSE testing.
- MMS testing.
- Gateway testing.
- Control sequence testing.
- Interlocking testing.
Site Acceptance Test (SAT)
SAT verifies the installed system under actual site conditions.
Typical activities include:
- Checking physical wiring.
- Verifying IED installation.
- Testing communication links.
- Checking CT and VT circuits.
- Testing circuit-breaker interfaces.
- Verifying HMI indications.
- Testing remote SCADA communication.
- Performing end-to-end protection and control tests.
The FAT and SAT procedures should be developed from the project specifications and approved test documentation.
14. Common Engineering Mistakes
| Mistake | Consequence | Prevention |
|---|---|---|
| Incorrect IED model or firmware description | Configuration incompatibility | Verify hardware and firmware before engineering |
| Duplicate IP address | Communication instability | Maintain a controlled IP register |
| Incorrect GOOSE mapping | Wrong protection or control signal | Validate every publisher-subscriber relationship |
| Inconsistent SCL files | Missing or incorrect references | Maintain configuration revision control |
| Incorrect HMI mapping | Misleading operator indications | Perform point-to-point testing |
| Incorrect control authority | Unavailable or unauthorized operation | Verify local/remote and control permissions |
| Missing time synchronization | Incorrect event sequence | Test time synchronization across IEDs |
| Incomplete SCADA point mapping | Missing remote indications or controls | Compare the database with the approved point list |
| No communication-failure testing | Undetected system vulnerability | Test expected failure scenarios |
15. Training on GE SAS Engineering by Elec-Engg
Practical SAS engineering requires knowledge of protection relays, IEC 61850, GOOSE, MMS, SCL configuration, SCADA gateways, network design and testing.
Elec-Engg provides practical technical training by Dr Saeed Roostaee (Electrical Engineering).
Relevant training subjects include:
- GE Multilin relay configuration.
- GE substation automation architecture.
- IEC 61850 system engineering.
- GOOSE publisher and subscriber configuration.
- MMS datasets and reporting.
- SCL engineering and validation.
- Protection and control signal mapping.
- SCADA gateway integration.
- IEDScout and Wireshark diagnostics.
- SAS FAT and SAT.
- Substation automation troubleshooting.
Training is available through pre-recorded video courses, structured self-paced training, live online sessions, face-to-face delivery and customized in-house programs.
Visit https://elec-engg.com/ to explore available training or use https://elec-engg.com/contact/ for technical training inquiries.
Conclusion
GE SAS engineering requires a structured approach to system architecture, IED configuration, communication design, IEC 61850 engineering, HMI development and SCADA integration.
The quality of the final system depends on the consistency of engineering information across all devices and software platforms.
Protection settings, control logic, signal mapping, communication parameters and operator interfaces must be verified together.
A disciplined engineering workflow, complete configuration records and comprehensive FAT/SAT testing are essential for delivering a reliable substation automation system.
Frequently Asked Questions
1. Which software is used for GE SAS engineering?
The software depends on the equipment selected. GE Multilin relays use the applicable EnerVista tools for their respective product families. Other station-level and communication equipment may require separate engineering applications.
2. Can GE Multilin relays be integrated with third-party IEDs?
Yes, when the required communication services and data models are compatible. IEC 61850 can support multi-vendor integration, subject to device-specific implementation and engineering validation.
3. What is the difference between relay configuration and SAS engineering?
Relay configuration focuses on an individual IED’s protection, logic and communication settings. SAS engineering coordinates all IEDs, networks, gateways, HMI and control functions into one integrated system.
4. What is an SCD file?
An SCD file is a Substation Configuration Description containing system-level IEC 61850 configuration information, including relevant IED and communication descriptions.
5. Is GOOSE required in every SAS?
No. GOOSE is used where fast IED-to-IED communication is required and supported. Some applications may use hardwired signals or other communication arrangements.
6. What is the purpose of a SCADA gateway?
It provides the communication interface between the substation automation system and the remote control centre.
7. What is FAT in SAS projects?
Factory Acceptance Testing verifies the configured SAS against the project requirements before delivery or installation.
8. What is SAT?
Site Acceptance Testing verifies the installed system at the substation, including wiring, communication, protection, control and SCADA integration.
9. Why is time synchronization important?
It ensures that events from different IEDs can be compared in a meaningful chronological sequence during disturbance investigation.
10. What is the most important SAS engineering document?
There is no single document that replaces the complete engineering package. The SAS architecture, IED list, communication diagrams, signal lists, control philosophy, interlocking diagrams and approved configurations must remain consistent.
GE SAS, GE SAS Engineering, GE Multilin, Substation Automation, IEC 61850, SCL Engineering, GOOSE, MMS, SCADA Gateway, IED Configuration, HMI Engineering, FAT, SAT, Relay Configuration, Elec-Engg
Image
- GE SAS engineering architecture showing process, bay and station levels.
- Substation IED communication network topology.
- IEC 61850 SCL engineering workflow.
- GE Multilin relay engineering software workstation.
- Substation HMI single-line diagram.
- SAS FAT and SAT testing setup.