Sepam Relay Settings, Testing & Commissioning: Complete Practical Engineering Guide
- Introduction
- 1.1 Introduction to Sepam Settings Engineering
- 1.2 Sepam Engineering Software
- 1.3 General Settings Engineering Workflow
- 1.4 Important Engineering Considerations
- 2.1 Importance of CT Configuration
- 2.2 CT Ratio Verification
- 2.3 CT Polarity
- 2.4 VT Ratio Configuration
- 2.5 VT Connection Verification
- 3.1 Introduction
- 3.2 Pickup Current Calculation
- 3.3 Time-Current Characteristics
- 3.4 Example Calculation
- 3.5 Instantaneous Overcurrent Protection
- 4.1 Introduction
- 4.2 Residual Current Calculation
- 4.3 Earth Fault Detection Methods
- 4.4 Earth Fault Pickup Calculation
- 4.5 Important Considerations
- 5.1 Introduction
- 5.2 Grading Margin
- 5.3 Time-Current Coordination
- 5.4 Example of Grading
- 5.5 Coordination Verification
- 6.1 Introduction
- 6.2 Required Equipment
- 6.3 Basic Testing Procedure
- 6.4 Pickup Testing
- 6.5 Operating Time Testing
- 7.1 Introduction
- 7.2 Test Universe Modules
- 7.3 Overcurrent Protection Testing
- 7.4 Testing Multiple Protection Stages
- 7.5 Binary Signal Monitoring
- 7.6 Testing Report
- 8.1 Introduction
- 8.2 Binary Input Testing
- 8.3 Binary Output Testing
- 8.4 Important Testing Precaution
- 9.1 Introduction
- 9.2 Trip Circuit Verification
- 9.3 Circuit Breaker Functional Testing
- 9.4 Trip Time Measurement
- 10.1 Introduction
- 10.2 Example: Overcurrent Trip Logic
- 10.3 Logic Verification Checklist
- 10.4 External Blocking
- 10.5 Practical Logic Test
- 11.1 Introduction
- 11.2 Event Record Analysis
- 11.3 Disturbance Record Analysis
- 11.4 Practical Fault Investigation
- 11.5 Common Event Analysis Problems
- 12.1 Introduction
- 12.2 Stage 1: Documentation Review
- 12.3 Stage 2: Visual Inspection
- 12.4 Stage 3: Configuration Verification
- 12.5 Stage 4: Measurement Testing
- 12.6 Stage 5: Protection Function Testing
- 12.7 Stage 6: Binary Input and Output Testing
- 12.8 Stage 7: Trip Circuit Testing
- 12.9 Stage 8: Communication Testing
- 12.10 Stage 9: Final Functional Testing
- 12.11 Stage 10: Documentation and Handover
- Project 1: Sepam Feeder Overcurrent Protection
- Project 2: Sepam Transformer Feeder Protection
- Project 3: Sepam Motor Protection
- Project 4: Sepam Earth Fault Protection
- Project 5: Complete Omicron Testing Project
- Project 6: Complete End-to-End Commissioning
- 14.1 Relay Does Not Measure Current Correctly
- 14.2 Overcurrent Protection Does Not Operate
- 14.3 Unwanted Overcurrent Trip
- 14.4 Earth Fault Protection Operates Incorrectly
- 14.5 Relay Output Does Not Operate
- 14.6 Circuit Breaker Does Not Trip
- 14.7 Communication Failure
- Recommended Training Topics
- Who Should Attend?
- Training Methods
- 19. Frequently Asked Questions (FAQs)
Introduction
The correct configuration, setting, testing, and commissioning of protection relays are essential for ensuring the safe and reliable operation of electrical power systems. Even when a protection relay has advanced protection functions, its performance depends on correct engineering data, appropriate protection settings, accurate CT and VT connections, proper binary input/output configuration, and successful commissioning tests.
The Schneider Electric Sepam protection relay family is widely used in industrial plants, distribution substations, motor control centres, and medium-voltage electrical networks. Sepam relays provide protection, measurement, monitoring, control, and communication functions for feeders, transformers, motors, generators, and other electrical equipment.
This article presents a practical engineering guide to Sepam relay settings, protection calculations, secondary injection testing, Omicron CMC testing, binary input/output verification, trip circuit testing, protection logic validation, disturbance record analysis, and complete commissioning procedures.
The objective is to explain not only how to configure Sepam relays but also how protection engineers and commissioning engineers can verify that the complete protection system operates correctly under normal and fault conditions.
1. Sepam Relay Settings Engineering
1.1 Introduction to Sepam Settings Engineering
Sepam settings engineering involves configuring the protection functions and operational parameters of a relay according to the electrical system design, protection philosophy, equipment characteristics, and coordination requirements.
Before changing any relay settings, the engineer should understand:
- Electrical single-line diagrams (SLDs).
- Protection and control philosophy.
- CT and VT specifications.
- Transformer, motor, generator, and feeder ratings.
- Maximum and minimum short-circuit currents.
- Earthing system characteristics.
- Circuit breaker operating characteristics.
- Protection coordination study.
- Existing relay settings and approved setting sheets.
Incorrect settings can result in unwanted tripping, failure to clear faults, loss of selectivity, or damage to electrical equipment.
1.2 Sepam Engineering Software
Schneider Electric provides SFT2841 as the traditional engineering software for configuring and operating supported Sepam relay models.
The software allows engineers to perform several activities:
- Create and manage Sepam projects.
- Select the appropriate Sepam relay model.
- Configure protection functions.
- Enter protection settings.
- Configure logic and control functions.
- Configure communication parameters.
- Monitor measurements and operating status.
- Retrieve alarms and event records.
- Upload and download configurations.
- Perform maintenance and troubleshooting.
The available features depend on the Sepam series, hardware configuration, firmware, and installed options.
1.3 General Settings Engineering Workflow
A typical engineering workflow includes:
- Identify the installed Sepam model and hardware.
- Confirm the firmware and software compatibility.
- Obtain the approved protection setting calculation.
- Verify CT and VT ratios.
- Configure the protection functions.
- Enter the calculated pickup values and time delays.
- Configure protection curves and operating characteristics.
- Configure binary inputs and outputs.
- Configure trip and alarm assignments.
- Verify protection logic.
- Configure communication parameters.
- Save and document the project.
- Download settings to the relay.
- Compare online and offline configurations.
- Perform secondary injection testing.
1.4 Important Engineering Considerations
The engineer must distinguish between:
- Primary electrical quantities.
- Secondary CT and VT quantities.
- Relay measurement values.
- Protection pickup thresholds.
- Operating time settings.
- Logical assignments.
- Physical output contacts.
For example, an overcurrent pickup calculated as 400 A primary may correspond to 4 A secondary when a 500/5 A CT is used.
The correct conversion must be verified against the relay’s actual measurement input configuration.
2. CT and VT Ratio Configuration
2.1 Importance of CT Configuration
Current transformers provide scaled representations of primary system currents to the protection relay.
The CT ratio must be correctly configured because it affects current measurement, protection pickup calculations, metering, and fault analysis.
For example:
- CT primary rating: 600 A
- CT secondary rating: 5 A
- CT ratio: 600/5
- Transformation ratio: 120
If the primary current is 360 A:
\[ I_s=\frac{360}{120}=3A \]
The relay receives 3 A secondary.
2.2 CT Ratio Verification
Before configuring the CT ratio, verify:
- CT nameplate information.
- CT primary and secondary ratings.
- Protection core allocation.
- CT accuracy class.
- CT burden.
- CT polarity.
- CT wiring diagrams.
- CT secondary earthing.
- CT shorting and test terminal arrangements.
Protection engineers must also check whether the CT is suitable for the expected fault current and relay burden.
2.3 CT Polarity
CT polarity is particularly important for directional protection, differential protection, residual earth fault protection, and power measurements.
Incorrect polarity may cause:
- Incorrect directional protection operation.
- Incorrect residual current measurement.
- Unwanted differential current.
- Incorrect power measurement.
- Failure of protection functions.
CT polarity must be verified through wiring inspection and suitable injection or primary testing procedures.
Important safety note: Never open-circuit an energized CT secondary. Use approved shorting arrangements and test procedures.
2.4 VT Ratio Configuration
Voltage transformers provide scaled voltage signals to the Sepam relay.
For example:
- Primary voltage: 11 kV
- Secondary voltage: 110 V
- VT ratio: 11000/110
- Transformation ratio: 100
If the primary voltage is 10.5 kV:
\[ V_s=\frac{10500}{100}=105V \]
The relay must be configured according to the actual voltage input arrangement.
2.5 VT Connection Verification
Common VT arrangements include:
- Three-phase voltage measurement.
- Phase-to-phase voltage measurement.
- Phase-to-neutral voltage measurement.
- Open-delta residual voltage measurement.
- Broken-delta voltage measurement.
The engineer must verify the connection type supported by the particular Sepam model.
Incorrect VT configuration can affect:
- Undervoltage protection (27).
- Overvoltage protection (59).
- Directional overcurrent protection (67).
- Directional earth fault protection (67N).
- Frequency protection (81).
- Power and energy measurement.
- Synchronism-check functions where supported.
3. Overcurrent Protection Setting Calculations
3.1 Introduction
Overcurrent protection is one of the most frequently used protection functions in Sepam relays.
The ANSI device numbers are:
- 50: Instantaneous overcurrent protection.
- 51: Time-delayed overcurrent protection.
The protection function detects current exceeding a predefined threshold and initiates an alarm or trip after the configured operating time.
3.2 Pickup Current Calculation
The pickup current must be selected above the maximum expected normal operating current while remaining sufficiently sensitive to detect minimum fault currents.
Consider a feeder with:
- Rated load current: 400 A.
- CT ratio: 500/5 A.
- Selected pickup: 1.25 × rated load current.
Primary pickup:
\[ I_{pickup}=400\times1.25 \]
\[ I_{pickup}=500A \]
Secondary pickup:
\[ I_{secondary}=\frac{500}{500/5} \]
\[ I_{secondary}=5A \]
The engineer must confirm that the relay’s supported setting range includes this value.
3.3 Time-Current Characteristics
Sepam models support different overcurrent characteristics depending on the relay series and protection function.
Common IEC inverse-time characteristics include:
- Standard inverse.
- Very inverse.
- Extremely inverse.
- Long-time inverse, where supported.
The general IEC inverse-time equation is:
\[ t=TMS\times\frac{k}{(I/I_s)^\alpha-1} \]
Where:
- \(t\) = operating time.
- \(TMS\) = time multiplier setting.
- \(I\) = measured current.
- \(I_s\) = pickup current.
- \(k\) and \(\alpha\) = curve constants.
Typical IEC curve constants are:
| Curve | k | α |
|---|---|---|
| Standard inverse | 0.14 | 0.02 |
| Very inverse | 13.5 | 1 |
| Extremely inverse | 80 | 2 |
| Long-time inverse | 120 | 1 |
These constants describe the IEC curve equations; actual implementation and available curve options must be checked against the relay documentation.
3.4 Example Calculation
Consider:
- Pickup current: 500 A.
- Fault current: 2000 A.
- TMS: 0.1.
- Curve: Standard inverse.
Current multiple:
\[ M=\frac{2000}{500}=4 \]
Operating time:
\[ t=0.1\times\frac{0.14}{4^{0.02}-1} \]
\[ t\approx0.49s \]
This is the theoretical relay operating time before considering output contact delay and circuit breaker operating time.
3.5 Instantaneous Overcurrent Protection
Instantaneous protection operates without an intentional inverse-time delay when current exceeds its configured threshold.
The pickup must be selected based on:
- Maximum downstream fault current.
- Minimum upstream fault current.
- Feeder protection requirements.
- Transformer inrush considerations.
- Coordination with downstream devices.
- Protection philosophy.
A setting that is too low can cause unwanted tripping, while a setting that is too high may reduce protection sensitivity.
4. Earth Fault Protection Settings
4.1 Introduction
Earth fault protection detects abnormal current flowing through an earth fault path.
Common Sepam earth fault protection applications include:
- Feeder earth fault protection.
- Transformer earth fault protection.
- Motor earth fault protection.
- Sensitive earth fault protection.
- Directional earth fault protection, where supported.
Typical ANSI functions include 50N, 51N, 50G, and 51G, depending on the measurement arrangement and relay implementation.
4.2 Residual Current Calculation
For a three-phase system, residual current is calculated as:
\[ I_0=I_A+I_B+I_C \]
The residual earth fault current is:
\[ I_N=3I_0 \]
The exact quantity used by the relay depends on its measurement convention and protection function.
4.3 Earth Fault Detection Methods
Common methods include:
Residual connection of phase CTs
The relay calculates the residual current from the three phase current inputs.
Core balance CT
A dedicated toroidal CT measures the residual current directly.
Neutral CT
A CT installed in the transformer or generator neutral connection measures neutral current.
Directional earth fault measurement
The relay evaluates current and voltage quantities to determine the direction of the earth fault.
4.4 Earth Fault Pickup Calculation
Assume:
- Phase CT ratio: 400/5 A.
- Desired earth fault pickup: 40 A primary.
The equivalent secondary current is:
\[ I_s=\frac{40}{400/5}=0.5A \]
The relay’s configured earth fault pickup must be checked against the actual measurement input and function scaling.
4.5 Important Considerations
Earth fault settings must consider:
- System earthing arrangement.
- Solidly earthed neutral.
- Resistance-earthed neutral.
- Isolated neutral.
- Compensated earthing systems.
- Minimum earth fault current.
- Maximum earth fault current.
- CT accuracy and saturation.
- Cable charging current.
- Downstream coordination.
A setting suitable for a solidly earthed network may be unsuitable for a resistance-earthed or isolated-neutral system.
5. Protection Coordination and Grading
5.1 Introduction
Protection coordination ensures that the protection device closest to the fault operates first while upstream devices provide backup protection.
The objective is to isolate the minimum possible section of the electrical network.
For example, in a radial distribution network:
- Downstream feeder relay.
- Upstream incomer relay.
- Transformer backup protection.
- Utility source protection.
The downstream protection should normally clear the fault before upstream backup protection operates.
5.2 Grading Margin
The grading margin is the time difference between the operating times of two successive protection devices.
It must account for:
- Relay operating time.
- Circuit breaker opening time.
- Relay overshoot and tolerances.
- CT errors and transient performance.
- Protection function characteristics.
- Engineering safety margins.
There is no single universal grading interval suitable for every installation.
5.3 Time-Current Coordination
A coordination study should compare the time-current characteristics of:
- Downstream Sepam relay.
- Upstream Sepam relay.
- Transformer protection.
- Fuse characteristics.
- Motor starting curves.
- Cable thermal limits.
- Circuit breaker operating characteristics.
The curves should be checked over the complete relevant fault current range.
5.4 Example of Grading
Consider two relays:
| Parameter | Downstream relay | Upstream relay |
|---|---|---|
| Fault current | 2000 A | 2000 A |
| Operating time | 0.25 s | 0.65 s |
| Time difference | – | 0.40 s |
The 0.40-second difference is the available grading interval in this example.
Whether this is acceptable depends on the equipment and protection coordination requirements.
5.5 Coordination Verification
The commissioning engineer should verify that:
- Pickup settings match approved calculations.
- Curve selections are correct.
- Time multipliers are correct.
- Instantaneous stages are coordinated.
- Earth fault stages are coordinated.
- Motor starting does not cause unwanted tripping.
- Transformer inrush is considered.
- Backup protection operates correctly.
6. Secondary Injection Testing
6.1 Introduction
Secondary injection testing verifies the protection relay’s response by injecting controlled current and voltage signals directly into its measurement circuits.
It is one of the most important commissioning and maintenance activities.
The test verifies:
- Measurement accuracy.
- Protection pickup values.
- Operating times.
- Protection characteristics.
- Directional functions.
- Logic operation.
- Alarm and trip outputs.
6.2 Required Equipment
Typical equipment includes:
- Protection relay test set.
- Current injection equipment.
- Voltage injection equipment.
- Multimeter.
- Laptop with compatible Sepam engineering software.
- Test leads and suitable adapters.
- Approved test documentation.
- Circuit diagrams.
6.3 Basic Testing Procedure
- Review the approved protection settings.
- Identify the Sepam relay model.
- Confirm CT and VT secondary ratings.
- Isolate the protection trip circuit where required.
- Connect the secondary injection test equipment.
- Verify the relay measurement values.
- Inject current below the pickup threshold.
- Confirm that the relay does not operate.
- Increase current above pickup.
- Measure the operating time.
- Repeat the test for different current values.
- Verify the alarm and trip indications.
- Restore the protection circuit.
- Record all test results.
6.4 Pickup Testing
Suppose the configured pickup current is 5 A.
The engineer can test:
- 4.5 A: Below pickup.
- 4.9 A: Below pickup.
- 5.0 A: At nominal pickup.
- 5.1 A: Slightly above pickup.
- 6.0 A: Above pickup.
The actual pickup threshold must be assessed according to the relay’s specified accuracy and test methodology.
6.5 Operating Time Testing
For time-delayed protection, the test set injects a specified current and measures the interval between current injection and the relay’s trip output.
The measured time is compared with the theoretical operating time and the manufacturer’s tolerance.
The testing report should include:
- Function tested.
- Pickup setting.
- Injected current.
- Current multiple.
- Expected operating time.
- Measured operating time.
- Acceptance criteria.
- Pass/fail result.
7. Omicron CMC Testing of Sepam Relays
7.1 Introduction
The OMICRON CMC 356 is widely used for protection relay testing and commissioning.
When combined with Test Universe, it provides a flexible platform for testing protection functions, measurement circuits, logic, and relay operating characteristics.
Sepam relays can be tested using suitable current and voltage injection arrangements and compatible test connections.
The precise test configuration depends on the CMC model, installed options, Sepam model, and relay wiring.
7.2 Test Universe Modules
Depending on the available software license, commonly used modules include:
- QuickCMC.
- Overcurrent.
- Ramping.
- State Sequencer.
- Advanced TransPlay.
- Differential.
- Distance.
- Transient-based testing tools.
Not every module is required for every Sepam application.
7.3 Overcurrent Protection Testing
The Overcurrent module can be used to verify:
- Pickup current.
- Operating time.
- Inverse-time characteristics.
- Instantaneous overcurrent.
- Multiple protection stages.
- Reset behavior where applicable.
Typical test procedure:
- Open Test Universe.
- Create a new test object.
- Select the Overcurrent module.
- Configure the current input channels.
- Enter the CT secondary rating.
- Enter the protection pickup setting.
- Select the applicable characteristic.
- Enter the time multiplier.
- Configure the trip signal.
- Connect the CMC test outputs.
- Run the test.
- Compare measured and expected results.
- Save the test report.
7.4 Testing Multiple Protection Stages
A Sepam relay may have several overcurrent stages.
For example:
- Stage 1: Low-set time-delayed overcurrent.
- Stage 2: High-set overcurrent.
- Stage 3: Instantaneous overcurrent, if available.
Each stage should be tested independently.
The engineer should also verify the correct output assignment and logical relationship between stages.
7.5 Binary Signal Monitoring
The CMC binary inputs can monitor relay output contacts.
For example:
- Binary Input 1: Overcurrent trip.
- Binary Input 2: Earth fault trip.
- Binary Input 3: General alarm.
- Binary Input 4: Circuit breaker status.
The engineer must configure the appropriate binary input polarity and contact logic.
7.6 Testing Report
The final Omicron report should contain:
- Relay identification.
- Sepam model.
- Firmware information.
- Protection function.
- Test module.
- Injected quantities.
- Measured operating times.
- Test tolerances.
- Pass/fail results.
- Engineer identification.
- Test date.
8. Binary Input and Output Testing
8.1 Introduction
Binary inputs and outputs provide the interface between the Sepam relay and the external electrical control system.
Binary inputs receive status signals, while binary outputs transmit commands and indications.
Typical applications include:
- Circuit breaker position.
- Disconnector position.
- Protection blocking.
- External trip.
- Local/remote selection.
- Spring-charged indication.
- Protection alarm.
- Circuit breaker trip.
- Circuit breaker close command, where supported.
8.2 Binary Input Testing
Each binary input should be tested individually.
Example:
| Input | Function | Expected indication |
|---|---|---|
| BI1 | CB closed | Closed |
| BI2 | CB open | Open |
| BI3 | External trip | Active |
| BI4 | Protection blocking | Active |
| BI5 | Local/remote | Remote |
The actual signal allocation must follow the approved control wiring diagram.
8.3 Binary Output Testing
Binary outputs should be tested by activating the assigned relay logic or by using approved testing facilities.
Example:
| Output | Function |
|---|---|
| BO1 | Main trip |
| BO2 | General alarm |
| BO3 | Earth fault trip |
| BO4 | Watchdog alarm |
The engineer must verify:
- Contact operation.
- Contact type.
- Contact rating.
- Electrical continuity.
- Output assignment.
- External circuit response.
- Reset behavior.
8.4 Important Testing Precaution
Never operate a physical trip or close output without understanding the connected circuit.
Before testing, identify whether the output is connected to:
- Circuit breaker trip coil.
- Circuit breaker closing coil.
- Lockout relay.
- Annunciation system.
- SCADA system.
Isolate the relevant circuits where necessary and follow approved switching and safety procedures.
9. Trip Circuit and Circuit Breaker Testing
9.1 Introduction
A protection relay can correctly detect a fault but still fail to isolate the electrical equipment if the trip circuit or circuit breaker is defective.
Therefore, commissioning must verify the complete trip chain.
The typical trip chain is:
Protection function → Relay logic → Output contact → Trip circuit → Circuit breaker trip coil → Circuit breaker opening
9.2 Trip Circuit Verification
The engineer should check:
- DC auxiliary supply.
- Fuse and MCB condition.
- Trip circuit continuity.
- Relay output contact.
- Trip coil resistance.
- Trip circuit supervision.
- Circuit breaker auxiliary contacts.
- Trip indication.
- Lockout relay operation, where installed.
9.3 Circuit Breaker Functional Testing
Typical tests include:
- Verify circuit breaker open and closed indications.
- Verify local opening.
- Verify remote opening.
- Verify protection trip.
- Verify closing operation.
- Verify anti-pumping function.
- Verify interlocking.
- Verify mechanical operation.
- Verify trip coil supervision.
- Record circuit breaker operating time.
9.4 Trip Time Measurement
The total fault clearing time consists of:
\[ t_{total}=t_{relay}+t_{CB} \]
Where:
- \(t_{relay}\) = protection relay operating time.
- \(t_{CB}\) = circuit breaker opening time.
For example:
- Relay operating time: 0.35 seconds.
- Circuit breaker opening time: 0.06 seconds.
\[ t_{total}=0.41s \]
This is the approximate total time from the start of the relay measurement condition to breaker interruption, subject to the timing reference and actual breaker behavior.
10. Protection Logic Verification
10.1 Introduction
Sepam protection relays provide programmable logic and control capabilities depending on the model and configuration.
Protection logic determines how protection elements, binary inputs, blocking signals, and output contacts interact.
A protection function may detect a fault without producing a trip if the logic is blocked or the output assignment is incorrect.
Therefore, logic verification is essential.
10.2 Example: Overcurrent Trip Logic
A simplified overcurrent trip logic can be represented as:
Phase Overcurrent Stage 1
|
v
Pickup Detected
|
v
Time Delay Expired
|
v
Protection Not Blocked
|
v
Trip Logic
|
v
Trip Output
|
v
Circuit Breaker Open
10.3 Logic Verification Checklist
Check the following:
- Protection function enabled.
- Correct pickup configuration.
- Correct time delay.
- Blocking signal inactive.
- Correct trip assignment.
- Correct output contact.
- Correct alarm assignment.
- Correct reset logic.
- Correct circuit breaker status feedback.
- Correct interlocking conditions.
10.4 External Blocking
External blocking may be used for:
- Busbar protection coordination.
- Downstream fault discrimination.
- Transformer protection.
- Motor starting.
- Interlocking arrangements.
The engineer must verify both the blocking input and the behavior of the affected protection function.
10.5 Practical Logic Test
Inject a fault current above the pickup threshold while keeping the blocking input active.
Expected result:
- The protection element may detect the fault.
- The assigned trip logic should respond according to the configured blocking philosophy.
- The physical trip output should behave as designed.
Then remove the blocking signal and repeat the test.
This confirms the interaction between the protection function and external logic.
11. Event and Disturbance Record Analysis
11.1 Introduction
Sepam relays provide diagnostic information that helps engineers understand system disturbances and protection operations.
Depending on the relay model, available records may include:
- Event records.
- Alarm records.
- Fault information.
- Disturbance or oscillography records.
- Measurements.
- Operating information.
- Communication diagnostics.
11.2 Event Record Analysis
Event records help identify the sequence of operations.
Example:
| Time | Event |
|---|---|
| 10:15:20.100 | Phase current increased |
| 10:15:20.120 | Overcurrent pickup |
| 10:15:20.450 | Overcurrent trip |
| 10:15:20.460 | Trip output activated |
| 10:15:20.520 | Circuit breaker opened |
This example illustrates how event timestamps can help establish the sequence of operation.
The actual recording resolution and timestamp accuracy depend on the relay and system configuration.
11.3 Disturbance Record Analysis
Where oscillography is supported, disturbance records can provide information about:
- Phase current waveforms.
- Phase voltage waveforms.
- Residual current.
- Voltage imbalance.
- Fault inception.
- Fault duration.
- Protection operation.
- Circuit breaker opening.
Engineers can use these records to determine whether the relay operated correctly and whether the fault was within the intended protection zone.
11.4 Practical Fault Investigation
Consider a feeder trip caused by phase overcurrent.
The engineer should investigate:
- Which phase experienced the highest current?
- Was the current above the pickup setting?
- Did the relay operate according to its configured curve?
- Was the trip delayed or instantaneous?
- Did the circuit breaker open correctly?
- Was there a downstream fault?
- Was the protection coordinated with upstream devices?
- Was the CT measurement accurate?
11.5 Common Event Analysis Problems
- Incorrect relay time synchronization.
- Missing event records.
- Incorrect time settings.
- Incomplete disturbance records.
- Incorrect CT polarity.
- Wrong phase identification.
- Inconsistent relay and SCADA timestamps.
Accurate time synchronization is especially important when comparing records from multiple protection relays and SCADA systems.
12. Complete Sepam Commissioning Procedures
12.1 Introduction
Commissioning confirms that the protection relay and associated electrical circuits are correctly installed, configured, tested, and ready for service.
A complete commissioning process must cover the entire protection chain rather than only the relay itself.
12.2 Stage 1: Documentation Review
Before testing, obtain:
- Approved single-line diagrams.
- Protection and control schematics.
- CT and VT drawings.
- Approved protection settings.
- Relay configuration files.
- Circuit breaker data.
- Cable schedules.
- Interlocking diagrams.
- Communication architecture.
- Commissioning test sheets.
12.3 Stage 2: Visual Inspection
Check:
- Relay model and serial number.
- Relay mounting.
- Auxiliary supply.
- Terminal connections.
- CT wiring.
- VT wiring.
- Earthing.
- Binary input wiring.
- Binary output wiring.
- Communication cables.
- Terminal tightness.
12.4 Stage 3: Configuration Verification
Verify:
- Relay identification.
- Hardware configuration.
- Firmware version.
- CT ratios.
- VT ratios.
- Protection settings.
- Protection curve selection.
- Time multipliers.
- Logic configuration.
- Output assignments.
- Communication parameters.
Save a backup of the approved configuration.
12.5 Stage 4: Measurement Testing
Verify the relay measurements using suitable test equipment.
Typical checks:
- Phase currents.
- Residual current.
- Phase voltages.
- Frequency.
- Power.
- Power factor.
- Energy measurements, where available.
Compare the relay measurements against the injected values.
12.6 Stage 5: Protection Function Testing
Test all protection functions that are enabled and included in the approved commissioning scope.
Examples:
- Phase overcurrent.
- Earth fault.
- Directional overcurrent.
- Undervoltage.
- Overvoltage.
- Negative sequence.
- Thermal overload.
- Frequency protection.
- Transformer differential.
- Motor protection.
The available functions depend on the particular Sepam model.
12.7 Stage 6: Binary Input and Output Testing
Verify every configured binary input and output against the approved wiring diagram.
Confirm that the relay correctly recognizes external signals and activates the intended contacts.
12.8 Stage 7: Trip Circuit Testing
Perform the approved trip circuit tests and confirm that the circuit breaker responds correctly.
Check trip coil circuits, breaker auxiliary contacts, trip supervision, and associated indications.
12.9 Stage 8: Communication Testing
Where communication is included in the project scope, verify:
- Ethernet or serial communication.
- Communication settings.
- Device address.
- Communication status.
- Modbus communication, where configured.
- IEC 61850 communication, where supported.
- SCADA indications.
- Alarm and measurement mapping.
Communication capability depends on the installed Sepam model and communication interface.
12.10 Stage 9: Final Functional Testing
Perform an end-to-end functional test.
For example:
- Inject a simulated fault condition.
- Verify relay pickup.
- Verify protection timing.
- Verify trip logic.
- Verify relay output contact.
- Verify trip circuit operation.
- Verify circuit breaker opening.
- Verify breaker status feedback.
- Verify event records.
- Verify SCADA indication, where applicable.
12.11 Stage 10: Documentation and Handover
Prepare:
- Approved final relay settings.
- Final configuration backup.
- Secondary injection reports.
- Omicron test reports.
- Binary input/output test sheets.
- Trip circuit test reports.
- Circuit breaker test reports.
- Communication test reports.
- Commissioning checklist.
- Outstanding punch list.
- Final commissioning certificate or handover report.
13. Practical Protection Testing Projects
The best way to develop Sepam engineering skills is through practical projects based on realistic electrical installations.
The following projects provide a structured approach to learning relay configuration and testing.
Project 1: Sepam Feeder Overcurrent Protection
Objective: Configure and test a feeder protection relay.
Activities:
- Review the feeder single-line diagram.
- Identify the CT ratio.
- Calculate the overcurrent pickup.
- Configure the 50/51 protection stages.
- Select the appropriate inverse curve.
- Calculate the operating time.
- Configure trip output.
- Test pickup current.
- Test operating time using Omicron.
- Verify the trip circuit.
Expected result: A fully configured and tested feeder protection function.
Project 2: Sepam Transformer Feeder Protection
Objective: Configure transformer feeder protection.
Activities:
- Review transformer rated power.
- Calculate full-load current.
- Verify CT ratios.
- Calculate phase overcurrent pickup.
- Calculate earth fault pickup.
- Consider transformer inrush.
- Coordinate with downstream and upstream protection.
- Perform secondary injection testing.
Expected result: Verified transformer feeder protection settings and test documentation.
Project 3: Sepam Motor Protection
Objective: Configure and test motor protection functions.
Activities:
- Enter motor rated current.
- Configure thermal overload protection.
- Configure phase overcurrent.
- Configure earth fault.
- Configure negative sequence protection, where available.
- Verify starting conditions.
- Test thermal and overcurrent functions.
- Verify trip and alarm outputs.
Expected result: A tested motor protection configuration consistent with the motor manufacturer’s data and protection study.
Project 4: Sepam Earth Fault Protection
Objective: Verify earth fault protection sensitivity and operation.
Activities:
- Identify the network earthing system.
- Identify the earth fault measurement method.
- Verify CT polarity and connections.
- Calculate the pickup setting.
- Configure the time delay.
- Inject residual current.
- Verify pickup and trip.
- Test blocking and alarm logic.
- Document the results.
Expected result: Verified earth fault protection performance.
Project 5: Complete Omicron Testing Project
Objective: Perform a complete protection relay test using Omicron CMC and Test Universe.
Activities:
- Create a Test Universe project.
- Configure the test object.
- Configure CT and VT ratios.
- Perform measurement checks.
- Test overcurrent pickup.
- Test inverse-time characteristics.
- Test instantaneous operation.
- Monitor binary outputs.
- Generate a test report.
Expected result: A professional protection relay testing report.
Project 6: Complete End-to-End Commissioning
Objective: Verify the entire protection and circuit breaker operating chain.
Activities:
- Inspect relay wiring.
- Verify relay configuration.
- Perform secondary injection.
- Verify protection logic.
- Test output contacts.
- Verify trip circuit.
- Operate circuit breaker.
- Check breaker auxiliary feedback.
- Verify events and indications.
- Prepare the final commissioning report.
Expected result: Complete commissioning documentation demonstrating the correct operation of the protection system.
14. Common Sepam Relay Failures and Troubleshooting
14.1 Relay Does Not Measure Current Correctly
Possible causes:
- Incorrect CT ratio.
- Incorrect CT wiring.
- Open CT secondary circuit.
- Loose terminal connection.
- Incorrect phase identification.
- Incorrect measurement configuration.
Troubleshooting:
- Verify the CT nameplate.
- Check the wiring diagram.
- Verify the secondary circuit.
- Inspect test terminal connections.
- Compare injected current with relay measurements.
- Verify configuration.
14.2 Overcurrent Protection Does Not Operate
Possible causes:
- Protection function disabled.
- Pickup setting too high.
- Fault current below pickup.
- Protection stage blocked.
- Incorrect time delay.
- Incorrect output assignment.
- Incorrect CT ratio.
Troubleshooting:
Check the measurement value, protection pickup status, function configuration, blocking conditions, timer status, and trip logic.
14.3 Unwanted Overcurrent Trip
Possible causes:
- Pickup setting too low.
- Incorrect CT ratio.
- Motor starting current.
- Transformer inrush.
- CT saturation.
- Incorrect protection coordination.
- Incorrect relay logic.
Troubleshooting:
Retrieve the event and disturbance records, compare actual current with the configured pickup, and review the approved coordination study.
14.4 Earth Fault Protection Operates Incorrectly
Possible causes:
- Incorrect CT polarity.
- Incorrect residual connection.
- Wrong earth fault pickup.
- Incorrect neutral earthing arrangement.
- Incorrect core balance CT wiring.
- Cable charging current.
- Incorrect directional voltage reference.
Troubleshooting:
Verify the earth fault measurement arrangement and compare injected residual current with the relay measurement.
14.5 Relay Output Does Not Operate
Possible causes:
- Incorrect output assignment.
- Faulty output contact.
- Incorrect protection logic.
- Blocking condition active.
- Incorrect relay configuration.
- Wiring problem.
Troubleshooting:
Verify the internal protection status, logic assignment, output contact, and external circuit independently.
14.6 Circuit Breaker Does Not Trip
Possible causes:
- Open trip circuit.
- Defective trip coil.
- Blown DC fuse.
- Incorrect auxiliary supply.
- Faulty output relay.
- Incorrect trip wiring.
- Mechanical circuit breaker problem.
Troubleshooting:
Test the complete trip chain systematically, following approved isolation and safety procedures.
14.7 Communication Failure
Possible causes:
- Incorrect communication settings.
- Incorrect device address.
- Wrong baud rate.
- Incorrect network configuration.
- Communication cable failure.
- Interface incompatibility.
- Incorrect protocol configuration.
Troubleshooting:
Check physical connections, communication parameters, device compatibility, and the status of the communication interface.
15. Sepam Relay Commissioning Checklist
The following checklist can be used during practical commissioning activities.
| No. | Commissioning activity | Status |
|---|---|---|
| 1 | Verify Sepam model and serial number | ☐ |
| 2 | Verify firmware and software compatibility | ☐ |
| 3 | Review approved drawings | ☐ |
| 4 | Verify auxiliary supply | ☐ |
| 5 | Inspect CT wiring and polarity | ☐ |
| 6 | Verify CT ratios | ☐ |
| 7 | Inspect VT wiring and polarity | ☐ |
| 8 | Verify VT ratios | ☐ |
| 9 | Verify protection settings | ☐ |
| 10 | Verify overcurrent protection | ☐ |
| 11 | Verify earth fault protection | ☐ |
| 12 | Verify other enabled protection functions | ☐ |
| 13 | Perform secondary injection testing | ☐ |
| 14 | Perform Omicron testing | ☐ |
| 15 | Verify binary inputs | ☐ |
| 16 | Verify binary outputs | ☐ |
| 17 | Verify protection logic | ☐ |
| 18 | Verify trip circuit | ☐ |
| 19 | Perform circuit breaker functional tests | ☐ |
| 20 | Verify communication | ☐ |
| 21 | Retrieve events and fault records | ☐ |
| 22 | Save final relay configuration | ☐ |
| 23 | Complete commissioning documentation | ☐ |
Note: This checklist is a general engineering template. Adapt it to the installed Sepam model, approved project specifications, manufacturer instructions, and site safety procedures.
16. Recommended Tools and Software for Sepam Engineering
The following tools are useful for Sepam relay configuration, testing, and commissioning.
SFT2841
Sepam configuration, protection settings, monitoring, diagnostics, and project management for supported Sepam models.
OMICRON Test Universe
Protection relay testing, pickup verification, operating time measurement, and automated test reporting.
OMICRON CMC Test Equipment
Secondary current and voltage injection for protection relay testing.
Sepam Protection Relays
Protection, measurement, monitoring, control, and communication for electrical installations.
17. Professional Training: Sepam Protection Relay Settings, Testing & Commissioning
Practical training is essential for engineers who want to develop professional skills in protection relay configuration, testing, and commissioning.
Our technical training programs at Elec-Engg by Dr Saeed Roostaee focus on practical engineering applications rather than only theoretical explanations.
The training approach combines protection principles, real engineering examples, software demonstrations, configuration exercises, and practical testing procedures.
Recommended Training Topics
- Sepam relay family and hardware architecture.
- Sepam protection functions and applications.
- SFT2841 software engineering.
- CT and VT configuration.
- Protection setting calculations.
- Overcurrent and earth fault protection.
- Protection coordination and grading.
- Secondary injection testing.
- Omicron CMC and Test Universe.
- Binary input and output testing.
- Trip circuit and circuit breaker testing.
- Protection logic verification.
- Event and disturbance record analysis.
- Complete relay commissioning procedures.
- Troubleshooting real protection problems.
Who Should Attend?
- Protection engineers.
- Electrical commissioning engineers.
- Substation engineers.
- Electrical maintenance engineers.
- Testing and commissioning technicians.
- Industrial electrical engineers.
- Power system engineers.
Training Methods
- Structured online training.
- Recorded technical courses.
- Practical software demonstrations.
- Customized company training.
- Face-to-face technical training.
- Realistic engineering case studies.
Explore our technical training programs:
Elec-Engg – Power System Protection & Substation Automation Training Pre-recorded Technical TrainingStructured Self-Paced Company Training
18. Conclusion
Sepam relay settings, testing, and commissioning require a systematic understanding of protection principles, electrical equipment characteristics, measurement circuits, relay configuration, and circuit breaker operation.
Correct CT and VT configuration, accurate protection settings, effective coordination, and comprehensive secondary injection testing are fundamental to reliable protection system performance.
Using tools such as SFT2841 and Omicron CMC, protection engineers can configure, verify, and document the operation of Sepam relays.
However, successful commissioning must go beyond testing individual protection elements. The complete protection chain—from current and voltage measurement through relay logic and output contacts to circuit breaker operation—must be verified.
A properly engineered and commissioned Sepam protection system improves electrical network reliability, minimizes unnecessary outages, and ensures that faults are detected and isolated correctly.
19. Frequently Asked Questions (FAQs)
1. Which software is used to configure Sepam protection relays?
SFT2841 is the traditional engineering software used for configuring, monitoring, and managing supported Sepam relay models.
2. Can Sepam relays be tested using Omicron CMC 356?
Yes. Suitable Sepam relays can be tested using Omicron CMC equipment and Test Universe through appropriate current, voltage, and binary signal connections.
3. What is secondary injection testing?
Secondary injection testing involves applying controlled current and voltage signals directly to the relay measurement circuits to verify protection functions and measurement accuracy.
4. What is the difference between 50 and 51 protection?
ANSI 50 represents instantaneous overcurrent protection, while ANSI 51 represents time-delayed overcurrent protection.
5. Why is CT ratio configuration important?
Incorrect CT ratios cause incorrect current measurements and can affect protection pickup, fault detection, and relay operation.
6. What is protection grading?
Protection grading coordinates the operating times and pickup characteristics of successive protection devices to isolate faults selectively.
7. What should be checked during Sepam commissioning?
CT and VT circuits, protection settings, measurement accuracy, protection functions, binary inputs and outputs, trip circuits, circuit breaker operation, communication, and event records.
8. Why might a Sepam relay fail to trip a circuit breaker?
Possible causes include incorrect protection logic, blocking signals, incorrect output assignments, defective output contacts, trip circuit failures, or circuit breaker problems.
9. Can all Sepam models perform the same protection functions?
No. Available functions depend on the Sepam model, hardware, firmware, and installed options.
10. Is testing the relay alone sufficient for commissioning?
No. The complete protection chain, including the relay, wiring, trip circuit, and circuit breaker, must be verified.