GE Multilin IEC 61850 SCL Engineering: ICD, IID, CID and SCD Files, System Configuration, GOOSE Mapping and Practical Workflow

Table Of Contents
  1. 1. Introduction
  2. 2. What Is IEC 61850 SCL?
  3. 3. Understanding the Main SCL File Types
  4. 4. Relationship Between GE Multilin Relay Configuration and SCL
  5. 5. SCL Engineering Workflow
  6. 6. Configuring MMS Datasets and Reports
  7. 7. Configuring GOOSE Communication Through SCL
  8. 8. Understanding External References
  9. 9. SCL Validation and Consistency Checks
  10. 10. Downloading and Applying the Configuration
  11. 11. Practical Example: Integrating Three GE Multilin Relays
  12. 12. Testing and Commissioning SCL Configurations
  13. 13. Troubleshooting Common SCL Problems
  14. 14. SCL Engineering Best Practices
  15. 15. SCL Engineering Documentation for a Substation Project
  16. 16. Frequently Asked Questions
  17. 17. Training on IEC 61850 SCL Engineering by Elec-Engg
  18. 18. Conclusion

1. Introduction

IEC 61850 Substation Configuration Language (SCL) is a fundamental part of engineering modern digital substations. When GE Multilin protection relays are integrated into an IEC 61850-based substation automation system, SCL files provide a standardized way to describe IED capabilities, communication parameters, logical nodes, datasets, report control blocks and GOOSE communication.

Correct SCL engineering is essential for reliable communication between protection relays, bay control units, station controllers and SCADA systems. Incorrect configuration can result in missing signals, failed GOOSE subscriptions, unavailable MMS reports, mismatched data references or unexpected behaviour during commissioning.

This article explains the practical use of ICD, IID, CID and SCD files in GE Multilin IEC 61850 engineering, including the relationship between relay configuration software, system configuration tools and SCADA platforms.

The exact SCL workflow depends on the GE Multilin relay family, firmware, IEC 61850 implementation and engineering software version. Not every relay supports every IEC 61850 service or configuration feature. Engineers must verify the supported functions for the exact device.

2. What Is IEC 61850 SCL?

SCL is an XML-based engineering language defined by IEC 61850-6. It describes the configuration of an IEC 61850 substation automation system.

An SCL file can contain information about:

  • Substation topology and primary equipment.
  • Intelligent Electronic Devices (IEDs).
  • Logical devices and logical nodes.
  • Communication networks and access points.
  • MMS datasets and report control blocks.
  • GOOSE control blocks and subscriptions.
  • External signal references.
  • Communication addressing and network parameters.

SCL provides a standardized way to exchange engineering information between compatible IED configuration tools and system configuration tools.

It does not automatically guarantee interoperability. Device-specific implementation, supported services, data models, firmware and engineering-tool compatibility must still be considered.

3. Understanding the Main SCL File Types

Several SCL file types are commonly used during IEC 61850 engineering.

3.1 ICD – IED Capability Description

An ICD file describes the IEC 61850 capabilities of an IED.

It generally contains:

  • IED identification.
  • Logical device structure.
  • Supported logical nodes.
  • Data objects and data attributes.
  • Available communication services.
  • Supported datasets and control blocks, where applicable.
  • Communication capabilities.

The ICD file is typically supplied or generated by the IED configuration tool.

For a GE Multilin relay, the ICD file should correspond to the exact relay model and the applicable firmware and IEC 61850 implementation.

An ICD file is not necessarily the final operational configuration of the relay. It primarily describes the capabilities available for system engineering.

3.2 IID – Instantiated IED Description

An IID file describes an instantiated IED configuration.

It can include configuration information associated with a particular IED instance, depending on the engineering workflow and tool implementation.

An IID file may be used to transfer an IED configuration from an IED-specific configuration environment into a system configuration environment.

Engineers should not assume that every GE Multilin configuration tool supports IID import or export in the same way.

3.3 CID – Configured IED Description

A CID file contains the configuration intended for a particular IED.

It may include:

  • IED identification.
  • Logical device and logical node configuration.
  • Communication parameters.
  • MMS datasets.
  • Report control blocks.
  • GOOSE control blocks.
  • GOOSE subscriptions.
  • Communication addressing.

The CID file is commonly associated with the configuration downloaded or transferred to an IED.

A CID file should be treated as device-specific. A CID generated for one relay model or firmware version should not be assumed to be suitable for another device.

3.4 SCD – Substation Configuration Description

An SCD file describes the overall IEC 61850 substation automation system.

It can include:

  • Substation structure.
  • Primary equipment.
  • All configured IEDs.
  • Communication networks.
  • IED access points.
  • Datasets.
  • Report control blocks.
  • GOOSE control blocks.
  • Publisher and subscriber relationships.
  • External signal references.

The SCD file is especially important when multiple IEDs exchange information through GOOSE or communicate with station-level SCADA systems.

It provides the system-level engineering context required to coordinate individual IED configurations.

3.5 Comparison of SCL File Types

FileMain purposeTypical engineering use
ICDDescribes IED capabilitiesImporting an IED into system engineering
IIDDescribes an instantiated IEDTransferring an IED instance configuration
CIDDescribes configured IED parametersConfiguring a particular IED
SCDDescribes the complete substation systemSystem-wide integration and coordination

The exact contents and supported exchange workflow depend on the engineering tools and implementation.

4. Relationship Between GE Multilin Relay Configuration and SCL

GE Multilin relays may use different configuration environments depending on the product family.

The engineering process can involve:

  1. Configuring protection functions and settings.
  2. Defining IEC 61850 logical devices and communication objects.
  3. Configuring datasets and report control blocks.
  4. Defining GOOSE publisher and subscriber relationships.
  5. Integrating the IED into the overall SCL system.
  6. Generating or importing the device-specific configuration.
  7. Downloading the configuration to the relay.
  8. Verifying communication and protection-related signals.

Protection settings and IEC 61850 communication settings are related but distinct engineering activities.

For example, a relay may correctly calculate a protection trip internally while the corresponding IEC 61850 indication is incorrectly mapped or unavailable to another IED.

Therefore, protection logic and communication mapping must be verified separately.

5. SCL Engineering Workflow

A practical SCL engineering project should follow a controlled workflow.

Step 1 – Identify the IED

Before starting, record:

  • Relay model.
  • Complete order code.
  • Hardware configuration.
  • Firmware version.
  • IEC 61850 edition and implementation.
  • Available Ethernet interfaces.
  • Supported MMS and GOOSE services.
  • Engineering software version.

This information helps avoid importing an incompatible IED description.

Step 2 – Obtain the Correct ICD File

Obtain the ICD file from the appropriate manufacturer engineering environment or documentation package.

Check:

  • Correct device model.
  • Correct firmware compatibility.
  • Logical node availability.
  • Data object names.
  • Supported services.
  • Dataset and control-block capabilities.
  • Communication access-point definitions.

Do not use an ICD file simply because its filename contains the same relay family name.

Step 3 – Create the Substation Project

In the system configuration environment, create the substation project.

Define the substation structure, voltage levels, bays and primary equipment as required by the engineering design.

A simplified substation structure may be:

  • Substation
    • 132 kV voltage level
      • Line Bay 1
      • Transformer Bay 1
      • Bus Coupler Bay
    • 33 kV voltage level
      • Feeder Bay 1
      • Feeder Bay 2

The SCL model can represent the relationship between primary equipment and the IEDs responsible for protection, control and monitoring.

Step 4 – Import the GE Multilin IED

Import the correct ICD or other supported IED description into the system configuration tool.

Assign a unique IED name.

For example:

  • GE_LINE_01
  • GE_TRANSFORMER_01
  • GE_FEEDER_01

IED names should be consistent with the project naming convention.

Check that the imported logical devices and logical nodes are available and that their data models correspond to the expected relay functions.

Step 5 – Configure the Communication Network

Define the communication architecture.

Typical parameters include:

  • Network name.
  • Subnetwork.
  • Ethernet access point.
  • IP address.
  • Subnet mask.
  • Gateway, where required.
  • VLAN configuration, where supported.
  • GOOSE multicast addressing.
  • Network redundancy arrangement, where supported.

Example engineering table:

IEDIP addressSubnet
GE_LINE_01192.168.10.11255.255.255.0
GE_TRANSFORMER_01192.168.10.12255.255.255.0
STATION_HMI192.168.10.100255.255.255.0

These addresses are illustrative only. Use the approved project network plan in an actual substation.

Ensure that IP addresses are unique and that the network design accounts for station-bus and process-bus separation where applicable.

6. Configuring MMS Datasets and Reports

MMS is commonly used for client-server communication between IEDs and station-level systems.

A station controller or SCADA client may read measurements, indications and equipment status from a GE Multilin relay.

6.1 Dataset Configuration

A dataset groups IEC 61850 data attributes for reporting or other supported services.

A feeder relay dataset might contain:

  • Circuit breaker position.
  • Protection trip indication.
  • Phase current measurements.
  • Phase voltage measurements.
  • Active power.
  • Reactive power.
  • Frequency.
  • Relay health status.

The actual logical node and data object references must be selected from the relay’s supported data model.

6.2 Report Control Blocks

Report control blocks define how data is reported to a client.

Depending on the relay implementation, available options may include:

  • Buffered reporting.
  • Unbuffered reporting.
  • Data-change reporting.
  • Quality-change reporting.
  • Data-update reporting.
  • Integrity reporting.
  • General interrogation.

Engineers should verify the available report-control options and their limits for the particular relay.

6.3 Example MMS Engineering Table

SignalExample purposeSCADA use
Breaker positionOpen/closed statusEquipment indication
Protection tripTrip eventAlarm and event
Phase currentCurrent measurementMetering
FrequencySystem frequencyMonitoring
Relay healthDevice supervisionMaintenance alarm

A correct dataset definition does not automatically guarantee that the SCADA client can access it. The client must also be configured with the correct IED, logical device, dataset and report-control references.

7. Configuring GOOSE Communication Through SCL

GOOSE communication is one of the most important applications of SCL in digital substations.

It allows IEDs to exchange event-driven information over Ethernet without relying on conventional point-to-point hardwired contacts for every signal.

7.1 Example: Feeder Protection Blocking

Consider two feeder relays connected to the same busbar.

A simplified blocking scheme may work as follows:

  1. A downstream feeder relay detects an overcurrent condition.
  2. It sends a blocking signal to an upstream relay.
  3. The upstream relay receives the blocking signal.
  4. The upstream relay delays its operation according to the coordination scheme.
  5. If the downstream fault is not cleared, the upstream protection operates according to the approved protection philosophy.

The actual protection logic, signal polarity, supervision and time coordination must be engineered and tested independently of the communication configuration.

7.2 Publisher Configuration

The publisher relay requires a GOOSE control block and a dataset containing the signals to be transmitted.

Typical engineering parameters include:

  • GOOSE control block reference.
  • Dataset reference.
  • GoID.
  • APPID.
  • Multicast MAC address.
  • VLAN ID.
  • VLAN priority.
  • Minimum and maximum retransmission intervals, as applicable.

The exact supported parameters depend on the relay and its IEC 61850 implementation.

7.3 Subscriber Configuration

The receiving relay must be configured to subscribe to the appropriate GOOSE message.

The engineer must verify:

  • Publisher IED identity.
  • GOOSE control block reference.
  • Dataset structure.
  • Data attribute mapping.
  • APPID.
  • Multicast MAC address.
  • VLAN configuration.
  • Expected data types.
  • Quality and validity handling.
  • Subscriber input mapping.

A GOOSE message appearing on the Ethernet network does not prove that the subscriber has correctly processed it.

7.4 Example GOOSE Signal Mapping

Publisher signalSubscriber functionEngineering purpose
Feeder protection blockingUpstream blocking inputGrading coordination
Breaker failure initiationBusbar trip logicBreaker failure scheme
Busbar trip indicationFeeder trip logicBusbar protection
Interlocking statusBay control logicSwitching interlocking

These examples describe typical applications. They must only be implemented when the relevant relay models support the required data objects, communication services and logic interfaces.

8. Understanding External References

External references are important for connecting published data to subscribed signals.

For example, a subscriber may reference a data attribute published by another IED.

A valid external reference must correspond to the actual publisher configuration.

Common problems include:

  • Incorrect IED name.
  • Incorrect logical device name.
  • Incorrect logical node.
  • Incorrect data object.
  • Incorrect data attribute.
  • Dataset mismatch.
  • Incompatible data type.
  • Missing or incorrect GOOSE control block reference.

A single incorrect reference can prevent a subscriber from receiving the intended signal.

Always compare the external reference against the publisher’s final configuration rather than relying on manually copied signal names.

9. SCL Validation and Consistency Checks

Before downloading configurations, perform a complete validation.

Check the following areas:

IED validation

  • Every IED has a unique name.
  • Each IED uses the correct description file.
  • Logical devices are correctly identified.
  • Logical nodes are available.
  • Data object references are valid.

Communication validation

  • IP addresses are unique.
  • Subnet configurations are correct.
  • Ethernet access points are correctly assigned.
  • VLAN parameters are consistent.
  • Multicast addressing is correct.
  • Network redundancy settings match the design.

MMS validation

  • Datasets contain the intended data attributes.
  • Report control blocks reference the correct datasets.
  • Client access is correctly configured.
  • Required report services are supported.

GOOSE validation

  • Publisher control blocks are correctly configured.
  • Subscribers reference the correct publishers.
  • Dataset structures match.
  • APPID and multicast MAC addresses are correct.
  • VLAN settings are consistent.
  • Subscriber input mappings are correct.
  • Signal quality and validity are considered.

Project validation

  • No unresolved external references remain.
  • No duplicate IED names exist.
  • No unintended configuration changes have been introduced.
  • The final SCD and device-specific configurations are archived.

10. Downloading and Applying the Configuration

The procedure for transferring SCL-derived configurations to GE Multilin relays depends on the specific product and engineering software.

A controlled process should include:

  1. Complete the SCL engineering.
  2. Validate the complete project.
  3. Generate the applicable device-specific configuration.
  4. Check compatibility with the relay model and firmware.
  5. Back up the existing relay configuration.
  6. Confirm the commissioning and operational authorization.
  7. Transfer the configuration using the supported procedure.
  8. Verify the relay’s communication parameters.
  9. Check MMS connectivity.
  10. Verify GOOSE publishing and subscription.
  11. Perform end-to-end functional tests.
  12. Archive the final configuration and test evidence.

Do not assume that importing an SCD file into an engineering tool automatically downloads the configuration to every IED.

In many workflows, the system configuration tool generates device-specific files that must then be transferred using the appropriate IED configuration environment.

11. Practical Example: Integrating Three GE Multilin Relays

Consider a substation with three protection IEDs:

  • GE_LINE_01 – line protection.
  • GE_TRANSFORMER_01 – transformer protection.
  • GE_FEEDER_01 – feeder protection.

The project requires:

  • MMS communication with the station SCADA.
  • GOOSE transfer of selected trip and interlocking signals.
  • Centralized event monitoring.
  • Communication supervision.

Engineering sequence

Stage 1 – IED preparation

Obtain the correct IED descriptions and verify the capabilities of each relay.

Stage 2 – System configuration

Create the substation structure and import the three IEDs.

Stage 3 – Network engineering

Assign IP addresses and configure the station-bus network.

Stage 4 – MMS engineering

Define the required datasets and report control blocks for SCADA monitoring.

Stage 5 – GOOSE engineering

Define publisher datasets and control blocks, then configure the intended subscriber relationships.

Stage 6 – Validation

Check all references, communication parameters and dataset structures.

Stage 7 – Device configuration

Generate and transfer the applicable configurations using the supported device-specific workflow.

Stage 8 – Commissioning

Test each communication service and verify the actual protection and control functions.

12. Testing and Commissioning SCL Configurations

SCL validation is not a substitute for physical and functional testing.

A complete commissioning procedure should include the following tests.

TestProcedureExpected result
IED identificationCompare configured and physical IED identityCorrect relay identified
IP connectivityPing or use an approved network diagnostic methodNetwork connectivity confirmed
MMS associationConnect with a compatible IEC 61850 clientMMS association established
Data modelBrowse logical devices and nodesExpected objects available
DatasetInspect configured dataset membersCorrect data references
ReportingTrigger a change of stateExpected report received
GOOSE publishingMonitor the publisher trafficCorrect GOOSE messages transmitted
GOOSE subscriptionInspect subscriber statusSubscription operates correctly
Signal mappingApply the relevant test inputCorrect subscriber input changes
End-to-end logicSimulate the intended protection or interlocking conditionCorrect functional response
Communication failureInterrupt the communication path under an approved test procedureCorrect supervision and fail-safe response

Important commissioning considerations

For protection-related GOOSE signals, testing should include:

  • Normal state.
  • Operated state.
  • Return-to-normal state.
  • Invalid or questionable quality.
  • Communication interruption.
  • Restoration after interruption.
  • Incorrect or missing subscription.
  • Behaviour during relay restart, where relevant.

For critical protection schemes, confirm the intended response to communication failure from the approved protection design. Never assume that loss of GOOSE communication automatically produces a trip, blocking or permissive response.

13. Troubleshooting Common SCL Problems

Problem 1 – ICD Import Failure

Possible causes:

  • Incorrect file format.
  • Unsupported SCL version.
  • Incompatible namespace.
  • Incorrect device description.
  • Unsupported logical node or service definition.

Recommended actions:

  • Obtain the correct ICD file.
  • Check compatibility with the system configuration tool.
  • Confirm the supported SCL schema version.
  • Review the engineering tool’s import diagnostics.

Problem 2 – GOOSE Subscriber Does Not Receive Data

Possible causes:

  • Incorrect publisher reference.
  • Incorrect APPID.
  • Incorrect multicast MAC address.
  • VLAN mismatch.
  • Incorrect dataset mapping.
  • Network multicast filtering.
  • Unsupported GOOSE implementation.

Recommended actions:

  • Inspect publisher traffic using an appropriate network analyzer.
  • Compare publisher and subscriber configuration.
  • Verify the network switch configuration.
  • Check the subscriber’s communication status.
  • Confirm the input mapping in the relay.

Problem 3 – MMS Communication Works but Reports Are Missing

Possible causes:

  • Incorrect report control block configuration.
  • Dataset mismatch.
  • Client not enabled or correctly associated.
  • Incorrect report trigger options.
  • Buffer or configuration limitations.
  • Unsupported reporting behaviour.

Recommended actions:

  • Browse the server data model.
  • Inspect the report control block.
  • Verify the dataset members.
  • Check client association and report enablement.
  • Test data-change and integrity reporting separately.

Problem 4 – SCD and CID Files Are Inconsistent

Possible causes:

  • Device configuration changed after SCD generation.
  • CID generated from an older project revision.
  • Incorrect IED instance.
  • Manual editing of XML.
  • Different engineering tool versions.

Recommended actions:

  • Establish one controlled project master.
  • Regenerate device-specific configurations from the approved system project where supported.
  • Compare file versions.
  • Revalidate the final configuration.
  • Record the revision applied to each relay.

Problem 5 – GOOSE Appears in a Network Capture but the Relay Input Does Not Change

Possible causes:

  • Incorrect external reference.
  • Wrong data attribute selected.
  • Subscriber mapping not completed.
  • Incompatible data type.
  • Invalid quality.
  • Incorrect application logic.
  • Configuration not transferred to the relay.

Recommended actions:

  • Inspect the actual GOOSE dataset.
  • Verify the subscriber reference.
  • Check the relay’s subscription diagnostics.
  • Confirm the input mapping and logic.
  • Perform a controlled end-to-end test.

14. SCL Engineering Best Practices

For reliable IEC 61850 projects, follow these practices:

  1. Maintain one approved master SCD project.
  2. Use consistent IED naming conventions.
  3. Use manufacturer-supported ICD files.
  4. Verify model and firmware compatibility.
  5. Maintain a controlled IP address register.
  6. Document every GOOSE publisher and subscriber relationship.
  7. Use meaningful dataset and control-block names.
  8. Avoid unnecessary datasets and excessive signal publishing.
  9. Validate the project before generating device-specific files.
  10. Keep backups of original and final relay configurations.
  11. Record firmware and configuration revisions.
  12. Perform end-to-end tests for protection-related signals.
  13. Maintain a GOOSE and MMS communication test record.
  14. Archive the final SCD, CID and applicable engineering files.
  15. Ensure that any manual XML modification is validated using an appropriate SCL validation tool.

15. SCL Engineering Documentation for a Substation Project

A professional IEC 61850 engineering package should include:

  • Approved SCD file.
  • Individual ICD files.
  • Final device-specific CID files, where applicable.
  • IED list and naming register.
  • IP address schedule.
  • Communication architecture.
  • MMS dataset list.
  • Report control block schedule.
  • GOOSE publisher and subscriber matrix.
  • VLAN and multicast addressing schedule.
  • IED firmware register.
  • Configuration revision register.
  • Commissioning test reports.
  • Backup and restoration procedure.

A well-maintained engineering package is particularly valuable during future maintenance, relay replacement, system expansion and fault investigation.

16. Frequently Asked Questions

What is the difference between ICD and CID files?

An ICD file describes an IED’s capabilities, while a CID file contains a configured description intended for a particular IED instance. The precise content depends on the engineering implementation.

What is the difference between SCD and CID?

An SCD file describes the complete substation automation system. A CID file describes the configuration intended for an individual IED.

Can an SCD file be directly downloaded to a GE Multilin relay?

Not necessarily. The system configuration tool may generate device-specific configuration files that must be transferred through the supported IED configuration workflow.

Is an ICD file specific to a relay model?

It should be selected according to the exact device and supported firmware or implementation. A generic or mismatched ICD file can cause engineering and interoperability problems.

Can GOOSE communication be configured using SCL?

Yes. SCL can describe GOOSE control blocks, datasets, communication parameters and publisher-subscriber relationships when supported by the IEDs and engineering tools.

Does successful SCL validation guarantee GOOSE operation?

No. SCL validation checks configuration consistency, but physical network connectivity, multicast delivery, device implementation and actual subscriber behaviour must also be tested.

Can GE Multilin relays communicate with Siemens SICAM PAS using IEC 61850?

Where the particular GE Multilin relay supports the required IEC 61850 services and data model, it may be integrated with a compatible SICAM PAS configuration. The exact model, firmware, supported services and client capabilities must be checked.

Which software should be used for SCL engineering?

The appropriate tools depend on the IED and system architecture. Use the supported GE Multilin IED configuration environment together with a compatible IEC 61850 system configuration tool. A third-party IEC 61850 client or analyzer can assist with testing and diagnostics.

17. Training on IEC 61850 SCL Engineering by Elec-Engg

Understanding SCL files is not enough to engineer a reliable digital substation. Protection and automation engineers must understand how IED capabilities, logical nodes, datasets, report control blocks, GOOSE communication and network configuration work together.

Elec-Engg provides practical technical training by Dr Saeed Roostaee (Electrical Engineering).

The training can cover:

  • IEC 61850 fundamentals and substation architecture.
  • Logical devices, logical nodes and data objects.
  • ICD, IID, CID and SCD file structures.
  • Practical SCL engineering and validation.
  • MMS datasets and report control blocks.
  • GOOSE publisher and subscriber configuration.
  • Integration of GE Multilin protection relays.
  • Integration with Siemens SICAM PAS and other compatible SCADA systems.
  • IEDScout-based communication analysis.
  • Wireshark-based MMS and GOOSE troubleshooting.
  • Practical testing and commissioning procedures.

Training delivery options include:

  • Pre-recorded technical video courses.
  • Structured self-paced training.
  • Live online training.
  • Face-to-face training.
  • Customized in-house training for utilities, EPC contractors and industrial organizations.

Explore the available technical courses and training programs:

Website: https://elec-engg.com/

Contact: https://elec-engg.com/contact/

18. Conclusion

SCL engineering provides the foundation for coordinating IEC 61850 communication across protection relays, bay control devices and station-level systems.

For GE Multilin installations, engineers must understand the roles of ICD, IID, CID and SCD files and how they relate to the actual relay configuration. Correct engineering requires careful management of logical nodes, communication parameters, MMS datasets, report control blocks, GOOSE publishers and subscribers.

The most important principle is that a valid SCL file is only one part of a successful digital substation project. Configuration consistency, device compatibility, network design, protection logic and end-to-end commissioning must all be verified before the system is placed into service.