– I have set the under-voltage limit at 9.4kV (94kv, pt ratio 11,000/110, But relay trips at 9.47kV. what to do?
– Make the vt connection vpp+vr. V peak to peak and v residual. In the configuration choose vpp+vr

– can support and provide abb 230kv gis maintenance procedures
Protection user x: I need a password for the DILO Sf6 Analyzer kit if someone can help
These P546 relays not reading the Remote end current what will be the issue?
– Is communication ok?
– Diff and bias current is reading and no alarm. Now the bay is charged, it’s not possible
– I think no problem because it will make a block for diff and the relay work distance only If there is a problem in configuration, the communication fails May will trip the line.

– What is the CT Ratio?
– 3000/1A bro
– If the load current increases the relay will trip
– Remote end is 1000/1A. What is the line distance

– in the p546 relay why are some signals not showing in Siemens sicam pas, pls tell me. But in the data set that signal is there. All signals appear at sicam pas no problem
– The problem is I can’t able to export icd file, only it’s showing iid, cid
– Need to perform a bit of boosting for this IED. Bit boosting process is a software update program for MiCOM Px20 platforms.
– Contact Schneider certified repair center, team

– I have 2 P546 relays, if any trip happens in relay one General trip LED is glowing. But in another relay only particular protection only the Gen trip LED is glowing, please let me know what is the issue?
– look in the front panel, menu system data, relay address, which address is set, if 255, try changing it to 1

– I have this Relay, I’m trying to change the IP address but I can’t edit it on the relay itself. How to change the IP address?
– This is an old version of Schneider make and firmware version relay.
You need to use IEC 61850 Configurator tool which is inbuilt in Easergy Studio to edit this information and send it via serial port initially to be able to see the IP address in the IED LHMI. I have the SEL serial port cable can I use it?
– better to change the MCL file. Easergy studio Series Port 9 pin cable and Bafo convert or some other converter
– I have managed to get the Bafo to convert and I have successfully changed the IP address


– I’m facing an issue with the P546 MCL file reporting with Siemens Scada. Scada engineer tells me that signals not reporting, check the static or dynamic settings. Where can I find this setting? But I add the report and control blocks
– Friends I’m facing an issue with the P546 MCL file reporting with Siemens Scada. Scada engineer tells me that signals not reporting, check the static or dynamic settings.


– I have connected the two winding currents of this relay and I can read the right currents on the relay (P645). But now I want to send back the Trip signals to RTDS but I have a problem with the Binary output of this Relay. On the schematics I can’t find out exactly the right binary output, can anyone help me, please.

-The back view of the relay and on C and E it’s where I have connected winding currents.
– These are the schematics I got from the manual. The relay serial number is 837922
– In MICOM always the binary output hardware slot is next to the power supply module. In your case, it is H and G slots for the 16 numbers of outputs in total as per your scheme and actual hardware
– Thank you, I have done the connection and the relay can send back the Trip signals to RTDS.`


– when I’m sending the MCL file I get these errors, what can be the problem. On this Relay P645.

– You can direct download the data model from the server.

– I have micom p443 distance relay & I face a problem when testing it through quick CMC. I didn’t get good reach results for quad (ground fault}.
– this may happen if you did not provide enough auxiliary voltage to the power supply module. i assume the relay was in a Healthy state before the problem in that case is related to the Processor card. Option-1.We need to inform GE (Formally Areva-ALSTOM) that they try to update the firmware via a parallel port using the Px40 download & calibration tool to the healthiness of the IED processor board(chances are very less to make the IED healthy in this method).
Option 2:Isolate the IED if it is part of the energized bay and replace the front HMI case along with the processor board if you have the same model and version spare replay.
Option-3: Contact GE and they will support you with the new healthy processor card loaded with the right

For joining our discussion groups: https://elec-engg.com/whatsapp-group-for-protection-engineers/


– Can anyone help with this error code? What does it mean?
– you can check this information in the MiCOM relay manual of Troubleshooting->Error Message/Code on the Powe up section
in your case, it is related to 0x0c0e which means the problem is related to the output modules in the faulty relay. Maybe you can replace from spare relays to make the relay healthy
– I mean just replace the output modules only from the front side of the relay. this problem is related to the processor card in the front, you need to replace the processor card from the spare relay which is having same model and firmware version in the order it makes the relay healthy
If the relay is within the warranty you can contact Schneider to replace it for free from their side, they will bring the spare processor card and update the firmware from their side/or send you the healthy processor card with the right firmware to the site. You need to install the latest connectivity package for the ieds that belong to the PCM project. You can manage the connectivity package from the update manager.
Check there do you have all the required versions installed for different product types.

PROTECTION RELAY SYSTEM ABB PCM 600
Elec-Engg.com

Elec-Engg.com support team: This is a discussion group and we can not share files here.

To share files and documents related to protection relay IEDs and IEC 61850, we created different WhatsApp groups. My colleague, Ali, manages these groups.

If you are interested in joining the groups, Please save the following number as Ali and text him ” join sharing group ” on WhatsApp: +989044686911

For joining our discussion groups: https://elec-engg.com/whatsapp-group-for-protection-engineers/

Please don’t hesitate if interested as limited members. 🙏
Protection user x:

– Can I clear the Tiz error through the software
– Software is not required. You can do it from the front of LHMI using key combinations.

I have an Abb relay rel 650 it cannot autoclose. the relay has CB ready all active and all status of the closed and open state.
– Did you check the events and what type of fault type (single-phase and other CB ready status also interlock input)?
-Ok, what type of fault scenario are you creating to check the autorecloser function?
– zone 1
– faulty is in zone 1
– Is it a single-phase fault or are you creating a fault in phase to phase (double/two-phase )or three phases?
– single-phase L1-E
– Ok, are you sure the relay is only receiving single-phase fault? Did you check in the DR?
– sir I checked in dr recorder


As u know, Elec-Engg’s main purpose is making video training in the field of substation automation and protection relays

🔻our courses: DIGSI 4 & 5, PSCAD, ETAP, ABB PCM600, IEC61850, Micom, Testing & commissioning, Generator protection, DigSILENT 🔺

PROTECTION RELAY SYSTEM IEC 61850
Elec-engg.com

– how to test open delta PT input to protection relay?
– depends on your setting, you can apply voltage and test it.


– I have this relay of Schneider P139, we just received it I am trying to energize it form auxiliary supply but its giving an error
Protection engineer user x: this is the display response when I apply the auxiliary power to switch on the relay. this is my connection where pin 4 and 3 are for DC supply and pin 1 and 2 I short it with the grounding. can anyone guide what can be the reason? why the relay is not turning ON? is there a connection problem or the problem with the relay itself?
– the power supply is set to 120V from FREJA 300. but when connected to this relay it SUDDENLY drops to 20V
– Relay load is more than Freja power supply. Use separate power source
– Check whether your model has that feature, Then enable in configuration.
-Have u checked the correct CB status and AR settings? Do a zone 1 trip and extract the events
– Conditions for AR in Schneider
1. Output contact should be assigned for Close Cmd.

  1. Keep Dead time less than Pole Disc time
  2. Keep trip mode in Single PH.
  3. Ensure CB status in 52a or 52b and ensure you have mapped same for CB Aux A, B, C.
  4. AR Block should be Zero.

For joining our discussion groups: https://elec-engg.com/whatsapp-group-for-protection-engineers/

– who can help me with the Schneider relay auto reclose issue. the C264 cannot even accept being connected
– Change the HMI from spare BCU. You need to remove the top and bottom cap first. Use screwdrivers to remove the HMI and change it from a healthy spare BCU.

Protection engineer user x: 1. Relay is not measuring any amps above 30, it is showing not measured.


  1. Please help in configuration of soft starter
    Protection engineer user x: Wat exactly psl or just settings?
    When relay connects to laptop this error will be showing continuous in every port
    Protection engineer user x: Pls resolve the issue
    Protection user x:Need help to configure the same, and also verify the settings. The relay is not displaying any current above 30 A,
    Protection engineer user x: The relay has been reset to factory defaults. So need your help to configure the relay.
    Protection user x: This is the setting file right
    Protection engineer user x: Yes sir.
    Protection user x: Drivers of the port were not found on the laptop. Download and install the USB drivers and the issue will be resolved. Thanks
    Protection engineer user x: Name of driver
    Protection user x: It depends on the RS232 to USB converter. Please share and image of the same we shall be able to guide you through.
    Protection user x: what’s the name of the converter, kindly share the data on it
    Protection engineer user x: Ok. Which version of windows are you using? 10 ?
    Protection user x: Window7
    Protection engineer user x: I need this software and probe
    Protection user x: i think you have to change your windows. i had a problem last month . it was not working with windows 10 and change it with old versin of windows 7 and solved the problem
    Protection engineer user x: Can you please send a close up of the interface?

PROTECTION RELAY SYSTEM with G02 Substation Automation

Protection engineer user x: Please anyone have this file with English translation

For joining our discussion groups: https://elec-engg.com/whatsapp-group-for-protection-engineers/
Protection user x:

Protection engineer user x: Hey everyone .have anyone one experience working with this automate
Protection user x:

Protection engineer user x: Twido Plc Schneider
Protection user x: We didn’t get to communicate with this plc
Protection engineer user x: Hi everyone!

(Data format: Data bit, praity, bit rate), common address, size of common address, link address, size of link address etc.

Protection user x: can we have the same settings for different RTU,s. Please explain.
Protection engineer user x: All RTUs will have same configurations as IEC101 is a protocol, which means “set of rules to be followed” by everyone to use it.
Protection user x: Please, How can I get these set of rules ?
Protection engineer user x: Google it
Protection user x: Thanks
Protection engineer user x: why thanks.
Protection user x: Does anyone know Micom Agile relay reset password??

PROTECTION RELAY SYSTEM MICOM
Elec-Engg.com

help pl.
Protection engineer user x: AAAA
Protection user x: Ya thats working fine for accessing Relay locally,

But I can’t extract the relay settings in remote through agile software . It’s showing high level password is required while extracting settings in agile software
Protection engineer user x: You can use “OTTER” as level 1 access password
Protection user x: I’ll try 👍🏼
Protection engineer user x: it’s not working
Protection user x: Try Configurator
Protection engineer user x: How about “TAIL”
Protection user x: Ok I’ll try
Protection engineer user x:Ok I’ll try
Protection user x: Dear All
Today we will understand the concept of Harmonic wrt Power quality through actual experiment done 🙏🔥❤️
https://youtu.be/m2z_m-KCko8
Protection engineer user x: About IEC61850 please help
Protection user x: Dear All
Let us brush up the concept of Earthing (Grounding) and Bonding today ❤️🙏👍
https://youtu.be/O5Sq0ccUy_U
Protection engineer user x: Dear All
Let us clear the doubts about Earthing/ Grounding of Lightning Arrester by watching this video 🙏❤️👍
=share
Protection user x: Dear All
Power Cables have replaced overhead lines in many places….we must understand the Joint Bay concept associated with power cable…. 🙏👍❣️
https://youtu.be/0X70Ewcwwq4
Protection engineer user x: Does anyone have experience in working ABB Scada Multiprog wt Software in RTUtil ? help needed.
Protection user x: Why we use power supply with Interface mudloe IM and digital inputs and output mouduls at smtic S 5 plc
Protection engineer user x: This power supply convert from 220 v AC to 5 v DC why we use this at control panel
Protection user x: Factory report straight line graph
Protection user x:

Protection engineer user x:

Protection user x: Hai anyone have experience in GE agile Gateway configuration?? .. I have established connection with control centre but data is communicating due to date and time non synchronization. Pls help
Protection engineer user x: data is not communicating*
Protection user x: GE Agile GTW software
Protection engineer user x: Hello guys
I have a question
I am a substation automation system engineer
In my substation we were connecting ABB relays ( as bank capacitor) to our local network
But every time we connect the fiber cables to ABB relays
The whole network become down
Anyone has an explanation!
Protection user x: Is that relay have RSTP nic port?
Protection engineer user x: RSTP must be enabled with priority settings in all switchs.
Protection user x: RSTP priority should be configured higher value on IED than other switches in network
Protection engineer user x: It is HSR loop bro not RSTP
Protection user x: What is HSR?
Protection engineer user x: What help is needed?
You can call 9740067460
Protection user x: High-availability Seamless Redundancy is a network protocol for Ethernet that provides seamless failover against failure of any single network componen.
Google it for more info

For joining our discussion groups: https://elec-engg.com/whatsapp-group-for-protection-engineers/

WhatsApp Chat with Test & Commissioning

Protection user x: Dear colleagues, DC converter loos AC incomer,(a &b) and they don’t switch to battery operation??? Any support
Protection engineer user x: Please i need your emergency support. The battery rack was ok 125v, sundly when rectifier loos the both incomer no current from battery and total voltage only 15v after 20sec
Protection user x:


Protection engineer user x: How to calculate zone 2 setting for radial feeder ???
Protection user x: Check battey individual voltage… Once
Protection engineer user x: Generally it is line impedence + 50% of adjecent shortest line for zone II.
Protection user x: Believe your batteries are not getting charged in reality. Please check what is the advised float & boost charging Volts, what is recommended charging current and once you complete 1st charge, conduct a discharge test to assure that the batteries are ready for backup.
Protection engineer user x: I had one similar case in my 1st project (25 years back), the charging voltage was not correct and charging current for float charge was also found to be set on lower side.
Protection user x: This may also be possible with very old electrolyte and storage beyond recommended time by manufacturer with electrolyte filled in cells and without charge
Protection engineer user x: Finally we found 1cell failed, we changed it.now ok
Protection user x: Good
Protection engineer user x: An other problem my friends.
During battery run down test we found the size of the cable from DC panel to DC motor is not enough (motor current more than normal current because high voltage drop).
We doubled the size. From the beginning of the new test the current value is high abd it is not correspond to the voltage value and current value for +1 higher-up than+2
-1 higher than -2
+1 129A
+2 149A
-1 129A
-2 149A
What do you think, terminal lug not connected properly???
Protection user x: One of the most important skills that a relay test engineer must possess is how to administer the test, meaning that he must know in advance what test is required of him? What is the number of wires that must be provided? , What type of relay should be tested, and how to connect it to the laptop? How to connect to the injection device, and is it possible to use Dry Contact or Wet Contact from the panel as feedback to the injection device?

Enjoy learning some of these skills in this special episode…
Protection engineer user x: I need password for DILO Sf6 Analyzer kit if someone can help

Protection user x: Dear colleagues, any batteries discharge and charge procedure. I need your support
Protection engineer user x:


Dear colleagues any support
Protection user x: Dear colleagues any training for hsbt soft
Protection engineer user x: There are some topics that if the protection engineer cannot understand them in depth, he will always be unable to explain and understand many phenomena that arise due to faults.One of the most important of these topics is the topic of Symmetrical Components, where the importance of this topic lies in being the only way to understand the current distributions on the three phases in the case of Unsymmetrical Faults.When a failure occurs like L-G-1 on Phase-A, the protection engineer always asks: Are other phases affected even though they are not involved in the failure? How much is their participation rate?
In addition to another important question about the effect of the type of transformer present in the network (eg star/delta or delta star etc) on the value of the fault current.All these questions and others can only be answered by a prevention engineer by understanding the topic of Symmetrical Components.Watch this episode to learn more details about this topic.
https://www.youtube.com/watch?v=Ilz9CcIcLCE
Protection user x: Dear colleagues any support to solve this pb,
Protection engineer user x: How to increase SP value in the controller.. anyone can help us..
Protection engineer user x:


Protection user x: Anyone can help
how we can avoid this display error?
Relay ABB REF615
Protection user x: Hope the below may help you…
Protection engineer user x: This youtube video says, it is private,not showing
Protection engineer user x:
Dear colleagues, any one has experience with fuse blown signal used in this drawing
Protection user x: Hello any body having digsi serial numberBackup IDMT trip means from Red615?
Protection engineer user x: It’s possible?

Protection engineer
REF stability
star star transformer
Siemence SIPROTEC5 BCU 6MD
goose with omicron
SEL relay
SEL relay software
DIGSI 4
MiCOM P142 relay
micom p441
IEC 60870-5

CMC356

DILO Sf6 Analyzer
Siemens sicam pas
icd file
MiCOM
micom p122
Schneider
Easergy studio
P546 MCL
Scada
GOOSE
data model
MiCOM relay manual
autoreclose
IEDScout
Micom, Testing & commissioning
schneider P139


Protection user x: Seems to be connected to be initiated by tripping command from RED615. Works like initiation of Breaker failure that will depend on CB status or connected via 52a
Protection engineer user x: Good day

Kindly assist with Reyroll LMT 6.6-30kV switch gear Factory Acceptance Results or typical test reports.

We would like to confirm the required results for ductor test, speed of operation, insulation resistance.
Protection engineer user x: Pls comments for CT connection terminals
Protection user x: You have this type of drawings for sneider Recloser?
Protection engineer user x: This message was deleted
Protection user x: This message was deleted
Protection engineer user x: Anyone please share SERTEL GPS engineer phone number
Protection user x: India
Protection engineer user x: Anybody here can help me with default ip of Alstom CSD RPH3??
Protection user x: How much DC current a typical tripping coil of 220kV circuit breaker draw during operation?
Protection engineer user x:


Dear colleagues, any support for this problem of load sharing in DC charger
Protection user x: Hi
Protection engineer user x: I have commissioning transftomer 33kV
Protection user x: ct in the transformer got fail for ratio accuracy for HV side
Protection engineer user x: But for LV ok, any info can share
Protection user x: Im using Ct analyser
Protection engineer user x: Omicron
Protection user x: did you ground the other transfomer bushing which not under test
Protection engineer user x: Ermm. Not..if the ct at yellow phase, Dyn11, do i need to ground also?
Protection user x: 1s1 and 1s3 Pass but for 1s1 and 1s2 failed
Protection user x: Could someone send Cable selection for 22kv and 66kv?
Protection engineer user x: Dear Sir, today i already done testing CT and did ground LV and phases that not involve with measurement
Protection user x: Result returned PASS
Protection engineer user x: Thanks Sir for your advise 👍👍
Protection user x: This is a discussion group and we can not share files here.

To share files and documents related to protection relay IEDs and IEC 61850, we created different WhatsApp groups. My colleague, Ali, manage these groups.

If you are interested in joining the groups, Please save the following number as Ali and text him ” join sharing group ” on WhatsApp:+989044686911

Please don’t hesitate if intereste as limited members. 🙏

PROTECTION RELAY SYSTEM IEC 61850
elec-engg.com

Protection user x: Good morning to all,
I hope you are doing well,
Kindly support from all of you,
Anybody having methid statement to battery discharge testing
Protection engineer user x: Please
Protection user x: What is ur bank capacity and cell voltage??
Protection engineer user x: 12V
Protection user x: Lead Acid battery
Fully charge cell voltage= 2.1
Min discharge cell voltage= 1.8
A 12V battery have 6 cells

Lets say u have a bank of 600AH of 110V. If U discharge it with the load bank of 4.4kW. The current will be 40 amp continuously flow up to battery reaches its discharge point.
Multiply the time (hr) with the 40 (current) and u will get the remaining capacity of bank.
Make a table accordingly. Sample I will share.
Protection engineer user x: Dear colleagues, our VT 15kv/100v were damaged and secondary cables were under very high temperature by mistake short circuit to ground.
Now new VT installed and the client requested to change a new cable but actually insulation resistance for these cables still ok no thing special.
Any advise??
Protection engineer user x: Better to change. VT is very sensitive in case of ground fault. It can burst/ blast and cause severe damage. Cable worth noting in front of that risk.
Protection user x: I will highly recommend
Protection engineer user x: And also better not to only consider IR. after dealing with temperature, physically insulation get harder and its integrity get weaker.
Protection user x: Good day. Kindly assist the best method/test equipment for on-line partial discharge testing of power cables.
Protection engineer user x: Dear colleagues, micome relay has trip coil supervision function ???
Protection user x: No
Protection user x:

For joining our discussion groups: https://elec-engg.com/whatsapp-group-for-protection-engineers/

Protection engineer user x: Anybody please explain to me..
Difference between CVT &IVT
Few place used in line bay-CVT
Few place used in line bay -IVT
What is the reason behind this?
Protection user x: Hi , anyone having PSM 641UX Motor protection and control device , relay settings program
Protection engineer user x: Dear colleagues, any online training of PLC??
Please support me

PROTECTION RELAY SYSTEM DIGSILENT
Elec-Engg.com

MICOM P123 protection relay has been made to control and protect current and ground faults for overhead and cable lines, and MICOM P441 is one of the distance relays that’s responsible for protection control and monitoring of transmission lines.

Through this course, you can learn how to configure and work with these relays.

  • Online video training
  • Trainer: Dr. Saeed Roostaee (Profile)
  • 4 hrs pre-recorded videos + 4 hrs attached supplementary videos on google drive + data models + PDF files

Part 01: MiCOM relays range, naming, and application

Parts 2-7: exercises with MiCOM P123 and AMT105 setup. Three-phase signals are injected into the relay to test hardware connection and protection functions.

Parts 8-17: exercises with MiCOM P441 and AMT105 (configuration and PSL, event and disturbance recorder, overcurrent protection, voltage protection, negative sequence protection, and distance protection parameters)

Download: Click here

Supplementary files attached

  • 01- start working with Easergy Studio in online mode
  • 02- MiCOM Relay Measurements, Event Logs & Disturbance Records
  • 03- Input naming in the Micom relays
  • 04- Communicate with MiCom P139
  • 05- Communicating with MICOM P139 checking the parameters from the front panel
  • 06- Binary input test from MICOM P139 front panel
  • 07- Binary input test from MICOM P139 front Easergy studio
  • 08 Function Parameters in the MICOM P139
  • 09- Overcurrent Function test in the Micom P139
  • 10- Inverse time overcurrent function IDMT test in the MiCOM P139
  • 11- CBF function config and parameters in the Micom P139
  • 12- Autorecoser function config in the MiCOMp139
  • 13- Autorecoser function test in the MiCOMp139
  • 14- Autorecoser function test in the MiCOMp139 By FREJA
  • 15- Under and Over Voltage protection function parameters and testing in the MiCOM P443
  • 16- Overcurrent and Earth Fault protection function parameters and testing in the MiCOM P443
  • 17- DEF protection function parameters and testing in the MiCOM P443
  • 18- Auto recloser function test in the MiCOM P546
  • 19- Trip Scheme in the Micom P546
  • 20- SOTF in the Micom P546
  • 21- MICOM P546 Differential protection test.
  • 22- MICOM P546 Syncro Check
MiCOM P123 front panel
Easergy Studio

Download: Click here

Certificate of Completion

After activating the MiCOM training pack on your system, we will issue your certificate for the course.

  1. M-1000: Click here to download
  2. M-1001: Click here to download
  3. M-1002: Click here to download
  4. M-1003: Click here to download
  5. M-1004: Click here to download
  6. M-1005: Click here to download
  7. M-1006: Click here to download
  8. M-1007: Click here to download
  9. M-1008: Click here to download
  10. M-1009: Click here to download
  11. M-1010: Click here to download
  12. M-1011: Click here to download
  13. M-1012: Click here to download
  14. M-1013: Click here to download
  15. M-1014: Click here to download
  16. M-1015: Click here to download
  17. M-1016: Click here to download
  18. M-1017: Click here to download
  19. M-1018: Click here to download
  20. M-1019: Click here to download
  21. M-1020: Click here to download
  22. M-1021: Click here to download
  23. M-1022: Click here to download
  24. M-1023: Click here to download
  25. M-1024: Click here to download
  26. M-1025: Click here to download
  27. M-1026: Click here to download
  28. M-1027: Click here to download